486 N CONCORD ST 90063

Certificate Information: 486 N CONCORD ST 90063

Application / Permit
23010-10000-04518
Plan Check / Job No.
B23LA21371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ADU
Permit Issued
Issued on 3/14/2024
Issuing Office
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 ARSALAN SHABESTARI
Corrections Issued 11/20/2023 ARSALAN SHABESTARI
Quality Review Completed 12/1/2023 KEN GILL
Building Plans Picked Up 12/11/2023 APPLICANT
Applicant returned to address corrections 3/6/2024 ARSALAN SHABESTARI
Plan Check Approved 3/14/2024 ARSALAN SHABESTARI
Issued 3/14/2024 APPLICANT
CofO in Progress 9/11/2025 CHARLES BOGHOSKHAN
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/21/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 11/22/2023 JESSICA OPINION
Sewer availability Cleared 11/22/2023 JESSICA OPINION
Low Impact Development (LID) Cleared 2/22/2024 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 2/24/2024 TREVOR QUAN
GPI Written Notices Cleared 3/6/2024 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 3/6/2024 ARSALAN SHABESTARI

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2024 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 4/12/2024 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 4/16/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 4/19/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 4/22/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/15/2024 Partial Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/20/2024 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 5/20/2024 Partial Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 5/23/2024 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/23/2024 Approved OSVALDO PARAMO
Wood Frame 5/23/2024 Corrections Issued OSVALDO PARAMO
Green Building Rough 5/24/2024 No Access for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/24/2024 No Access for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/28/2024 Approved OSVALDO PARAMO
Green Building Rough 5/28/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 5/28/2024 Approved OSVALDO PARAMO
Insulation 5/29/2024 Approved OSVALDO PARAMO
Drywall Nailing 6/5/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/5/2024 Approved ALIZAH MAYAGOITIA
Sewer 7/2/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 7/2/2024 Partial Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Final 9/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 9/2/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 9/2/2025 Approved ALIZAH MAYAGOITIA
Final 9/5/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 9/5/2025 Not Ready for Inspection LILIANA PORTILLO
Final 9/10/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 9/10/2025 Approved ALIZAH MAYAGOITIA