486 N CONCORD ST 90063
Certificate Information: 486 N CONCORD ST 90063
- Application / Permit
- 23010-10000-04518
- Plan Check / Job No.
- B23LA21371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 11/20/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/1/2023 | KEN GILL |
| Building Plans Picked Up | 12/11/2023 | APPLICANT |
| Applicant returned to address corrections | 3/6/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/14/2024 | ARSALAN SHABESTARI |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 11/22/2023 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 2/22/2024 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 2/24/2024 | TREVOR QUAN |
| GPI Written Notices | Cleared | 3/6/2024 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 3/6/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 4/12/2024 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 4/16/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/15/2024 | Partial Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 5/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 5/20/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 5/23/2024 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 5/23/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/23/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 5/24/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/24/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/28/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | OSVALDO PARAMO |
| Insulation | 5/29/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 7/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 7/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 9/2/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 9/2/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 9/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/5/2025 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 9/5/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 9/10/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 9/10/2025 | Approved | ALIZAH MAYAGOITIA |