6821-6821 1/2 E ELGIN ST 90042

Certificate Information: 6821-6821 1/2 E ELGIN ST 90042

Application / Permit
23010-10000-04496
Plan Check / Job No.
B23LA21250
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Proposed 2-story Detached 2 unit ADU (attached ADU's under separate permit). FULLY SPRINKLERED NFPA 13D
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 4/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 JOE VO
Corrections Issued 11/12/2023 JOE VO
Quality Review Completed 11/16/2023 PRANITA SHAH
Applicant returned to address corrections 4/24/2024 JOE VO
Plan Check Approved 5/1/2024 JOE VO
Issued 7/12/2024 APPLICANT
CofO in Progress 4/3/2025 DAVID WILLIAMS
No Progress 4/6/2025 DEROLD HAUFF
CofO in Progress 4/6/2025 DEROLD HAUFF
Permit Finaled 4/19/2025 DEROLD HAUFF
CofO Issued 4/19/2025 DEROLD HAUFF
Permit Finaled 4/19/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/25/2023 ADRIAN SANCHEZ
Highway dedication Cleared 11/25/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/6/2024 CHRISTINA BRACO
Sewer availability Cleared 2/6/2024 CHRISTINA BRACO
Hydrant and Access approval Cleared 4/15/2024 RUEL COLE
Low Impact Development (LID) Cleared 4/15/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 4/24/2024 CELINA MORENO
Grading Pre-Inspection Cleared 4/30/2024 JOE VO

Contact Information

Contractor Fort Multifamily Inc; Lic. No.: 1097435-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/25/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/25/2024 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/1/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/1/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/5/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 9/25/2024 Corrections Issued ALIZAH MAYAGOITIA
Insulation 9/25/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/25/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/7/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/7/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 10/7/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Corrections Issued ALIZAH MAYAGOITIA
Pre-Inspection 10/11/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/29/2024 No Access for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 No Access for Inspection ALIZAH MAYAGOITIA
Green Building Rough 10/29/2024 No Access for Inspection ALIZAH MAYAGOITIA
MERV13>=Rough 10/29/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 10/29/2024 No Access for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 10/29/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/1/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Partial Approval LUIS CASTRO
Green Building Rough 11/1/2024 Not Ready for Inspection LUIS CASTRO
MERV13>=Rough 11/1/2024 Not Ready for Inspection LUIS CASTRO
Pre-Inspection 11/1/2024 Not Ready for Inspection LUIS CASTRO
Verify Sprinkler Sign Off 11/1/2024 Approved LUIS CASTRO
Insulation 11/12/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/12/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 11/18/2024 Approved ANTHONY RAMOS
ELECTRICAL-Final 2/19/2025 Corrections Issued CRAIG DAVIS
HVAC-Final 2/19/2025 Corrections Issued CRAIG DAVIS
PLUMBING-Final 2/19/2025 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 2/26/2025 No Access for Inspection ALIZAH MAYAGOITIA
HVAC-Final 2/26/2025 No Access for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/26/2025 No Access for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/27/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/27/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/27/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/6/2025 Approved ALIZAH MAYAGOITIA
Final 3/6/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/6/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 3/6/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/6/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 3/6/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 3/6/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 3/6/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 3/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 3/6/2025 Approved ALIZAH MAYAGOITIA
Final 3/14/2025 Not Ready for Inspection DAVID WILLIAMS
Service/Power Release 3/14/2025 Conditional Approval DAVID WILLIAMS
Final 4/2/2025 Not Ready for Inspection DAVID WILLIAMS
Service/Power Release 4/2/2025 Not Ready for Inspection DAVID WILLIAMS
Final 4/3/2025 OK to Issue CofO DAVID WILLIAMS
Service/Power Release 4/3/2025 Approved DAVID WILLIAMS