6821-6821 1/2 E ELGIN ST 90042
Certificate Information: 6821-6821 1/2 E ELGIN ST 90042
- Application / Permit
- 23010-10000-04496
- Plan Check / Job No.
- B23LA21250
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed 2-story Detached 2 unit ADU (attached ADU's under separate permit). FULLY SPRINKLERED NFPA 13D
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- Current Status
- CofO Issued on 4/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | JOE VO |
| Corrections Issued | 11/12/2023 | JOE VO |
| Quality Review Completed | 11/16/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 4/24/2024 | JOE VO |
| Plan Check Approved | 5/1/2024 | JOE VO |
| Issued | 7/12/2024 | APPLICANT |
| CofO in Progress | 4/3/2025 | DAVID WILLIAMS |
| No Progress | 4/6/2025 | DEROLD HAUFF |
| CofO in Progress | 4/6/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
| CofO Issued | 4/19/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2023 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 11/25/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 2/6/2024 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 4/15/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 4/15/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/24/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/30/2024 | JOE VO |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/25/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/25/2024 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/1/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 9/25/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 9/25/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/25/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/7/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/7/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Pre-Inspection | 10/11/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/29/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/29/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 10/29/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 10/29/2024 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 10/29/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/1/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 11/1/2024 | Not Ready for Inspection | LUIS CASTRO |
| MERV13>=Rough | 11/1/2024 | Not Ready for Inspection | LUIS CASTRO |
| Pre-Inspection | 11/1/2024 | Not Ready for Inspection | LUIS CASTRO |
| Verify Sprinkler Sign Off | 11/1/2024 | Approved | LUIS CASTRO |
| Insulation | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/18/2024 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 2/19/2025 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 2/19/2025 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 2/26/2025 | No Access for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/26/2025 | No Access for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/26/2025 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/27/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/6/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/6/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/14/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Service/Power Release | 3/14/2025 | Conditional Approval | DAVID WILLIAMS |
| Final | 4/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 4/3/2025 | OK to Issue CofO | DAVID WILLIAMS |
| Service/Power Release | 4/3/2025 | Approved | DAVID WILLIAMS |