11382 W NUTMEG AVE 90066

Certificate Information: 11382 W NUTMEG AVE 90066

Application / Permit
23010-10000-04488
Plan Check / Job No.
B23LA21203
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN new 2-story detached ADU
Permit Issued
Issued on 7/18/2024
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 ARSALAN SHABESTARI
Corrections Issued 12/4/2023 ARSALAN SHABESTARI
Quality Review Completed 12/13/2023 GARO TELMI
Plan Check Approved 5/31/2024 ARSALAN SHABESTARI
Plan Check Approved 7/2/2024 ARSALAN SHABESTARI
Issued 7/18/2024 APPLICANT
CofO in Progress 2/2/2026 DAVID FEILER
No Progress 2/3/2026 DAVID FEILER
CofO in Progress 2/3/2026 DAVID FEILER
Permit Finaled 2/12/2026 RICHARD STEINBACH
CofO Issued 2/12/2026 RICHARD STEINBACH
Permit Finaled 2/12/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/18/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/24/2024 DARIN LAM
Sewer availability Cleared 1/24/2024 DARIN LAM
Specific Plan Cleared 1/30/2024 PEDRO AYALA
Construction near power lines Cleared 2/24/2024 RIDWAN HARDY
Construction within easement Cleared 2/24/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 5/8/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/13/2024 DARIN LAM

Contact Information

Architect Gaudio,, Kristin Drews; Lic. No.: NA35634       ,
Contractor Dixon Construction Inc; Lic. No.: 706524-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/25/2025 Approved RUBEN RIVAS
PLUMBING-Rough 3/25/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 3/28/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Partial Approval MICHAEL ALLEN
Sewer 4/17/2025 Approved JAYLIN GRAVITTE
PLUMBING-Rough 4/25/2025 Partial Approval BOBBY KEY
Underground Mechanical 4/25/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval MICHAEL ALLEN
Gas Test 5/15/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 5/15/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 5/16/2025 Approved MICHAEL ALLEN
HVAC-Rough 5/16/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Approved MICHAEL ALLEN
Green Building Rough 5/23/2025 Not Ready for Inspection MICHAEL ALLEN
Special/Order Compliance 5/23/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 6/9/2025 Approved MICHAEL ALLEN
Green Building Rough 6/9/2025 Not Ready for Inspection MICHAEL ALLEN
Special/Order Compliance 6/9/2025 Partial Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 6/12/2025 Approved RUBEN RIVAS
Special/Order Compliance 6/12/2025 Partial Inspection TEMISTOCLES CAAL
Insulation 6/18/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/18/2025 Corrections Issued MICHAEL ALLEN
Drywall Nailing 6/24/2025 Approved MICHAEL ALLEN
Shower Pan 6/24/2025 Approved MICHAEL ALLEN
Shower Pan 6/25/2025 No Access for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 7/2/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 10/16/2025 Approved RUBEN RIVAS
HVAC-Final 10/16/2025 Approved RUBEN RIVAS
PLUMBING-Final 10/16/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 10/24/2025 Approved WILBER ROSALES
Final 10/24/2025 Corrections Issued WILBER ROSALES
Green Building Final 10/24/2025 Approved WILBER ROSALES
Green Building Rough 10/24/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved WILBER ROSALES
Service/Power Release 10/24/2025 Not Ready for Inspection WILBER ROSALES
Smoke Detectors 10/24/2025 Approved WILBER ROSALES
Final 1/5/2026 Corrections Issued WILBER ROSALES
Service/Power Release 1/5/2026 Not Ready for Inspection WILBER ROSALES
Final 2/2/2026 OK to Issue CofO DAVID FEILER
Service/Power Release 2/2/2026 Approved DAVID FEILER