11382 W NUTMEG AVE 90066
Certificate Information: 11382 W NUTMEG AVE 90066
- Application / Permit
- 23010-10000-04488
- Plan Check / Job No.
- B23LA21203
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN new 2-story detached ADU
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 12/4/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/13/2023 | GARO TELMI |
| Plan Check Approved | 5/31/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 7/2/2024 | ARSALAN SHABESTARI |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 2/2/2026 | DAVID FEILER |
| No Progress | 2/3/2026 | DAVID FEILER |
| CofO in Progress | 2/3/2026 | DAVID FEILER |
| Permit Finaled | 2/12/2026 | RICHARD STEINBACH |
| CofO Issued | 2/12/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/12/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/24/2024 | DARIN LAM |
| Specific Plan | Cleared | 1/30/2024 | PEDRO AYALA |
| Construction near power lines | Cleared | 2/24/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/24/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 5/8/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/13/2024 | DARIN LAM |
Contact Information
| Architect | Gaudio,, Kristin Drews; Lic. No.: NA35634 | , |
| Contractor | Dixon Construction Inc; Lic. No.: 706524-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/25/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/25/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 3/28/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Partial Approval | MICHAEL ALLEN |
| Sewer | 4/17/2025 | Approved | JAYLIN GRAVITTE |
| PLUMBING-Rough | 4/25/2025 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 4/25/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | MICHAEL ALLEN |
| Gas Test | 5/15/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 5/15/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 5/16/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/16/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 5/23/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Special/Order Compliance | 5/23/2025 | Corrections Issued | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 6/9/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Special/Order Compliance | 6/9/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/12/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 6/12/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Insulation | 6/18/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 6/18/2025 | Corrections Issued | MICHAEL ALLEN |
| Drywall Nailing | 6/24/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 6/24/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 6/25/2025 | No Access for Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 7/2/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 10/16/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 10/16/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 10/16/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | WILBER ROSALES |
| Final | 10/24/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 10/24/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 10/24/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 10/24/2025 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 10/24/2025 | Approved | WILBER ROSALES |
| Final | 1/5/2026 | Corrections Issued | WILBER ROSALES |
| Service/Power Release | 1/5/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 2/2/2026 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 2/2/2026 | Approved | DAVID FEILER |