10830 S HICKORY ST 90059
Certificate Information: 10830 S HICKORY ST 90059
- Application / Permit
- 23010-10000-04465
- Plan Check / Job No.
- B23LA21100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY RESIDENCE AREA 1246 SF WITH A NEW 2 CAR GARAGE OF AREA 467 SF PLUS A NEW ATTACHED ADU OF AREA 993 SF. 121221
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JOHN MESIAS |
| Corrections Issued | 12/19/2023 | JOHN MESIAS |
| Quality Review Completed | 12/19/2023 | KESETE HAREGOT |
| Building Plans Picked Up | 12/22/2023 | APPLICANT |
| Applicant returned to address corrections | 10/8/2024 | JOHN MESIAS |
| Plan Check Approved | 10/24/2024 | JOHN MESIAS |
| Issued | 1/13/2025 | APPLICANT |
| CofO in Progress | 2/19/2026 | ARTHUR NEGRETE |
| Permit Finaled | 4/9/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/9/2026 | ANSON MAGLASANG |
| CofO Issued | 4/9/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | STEVEN JIN |
| Permit | Cleared | 4/5/2024 | STEVEN JIN |
| Hydrant and Access approval | Cleared | 5/20/2024 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2024 | STEVEN JIN |
| Sewer availability | Cleared | 5/29/2024 | STEVEN JIN |
| Trees in Parkway | Cleared | 8/26/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 9/27/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 10/11/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/28/2025 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 3/5/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/14/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/20/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/3/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/3/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 6/3/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/16/2025 | Conditional Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 7/16/2025 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Approved | JOHN KLARIN |
| Green Building Rough | 7/16/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/16/2025 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/16/2025 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 7/30/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/6/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/6/2025 | Approved | ANTHONY EGSON |
| Sewer | 11/4/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/3/2025 | Partial Approval | ARTHUR NEGRETE |
| ELECTRICAL-Final | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Final | 12/3/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 12/3/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 12/3/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 12/3/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 12/3/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 12/3/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 12/3/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/30/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Final | 1/30/2026 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 1/30/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/30/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 1/30/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/9/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/9/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Service/Power Release | 2/9/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/17/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/17/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 2/17/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/17/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/17/2026 | Approved | ARTHUR NEGRETE |