416 E AVENUE 39 90031
Certificate Information: 416 E AVENUE 39 90031
- Application / Permit
- 23010-10000-04425
- Plan Check / Job No.
- B23LA20934
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached ADU per state law CA GC 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). **SEE COMMENTS**
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | JOHNPAUL ISIP |
| Corrections Issued | 11/13/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/2/2023 | CAROLEAN BASMA |
| Plan Check Approved | 4/17/2024 | EDWIN ESPIN |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 2/24/2025 | LILIANA PORTILLO |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
| CofO Issued | 2/26/2025 | DEROLD HAUFF |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2023 | ARNULFO CHAMU |
| CPC | Cleared | 11/14/2023 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/14/2023 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/14/2023 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 11/17/2023 | ARNULFO CHAMU |
| HPOZ | Cleared | 11/29/2023 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 12/3/2023 | JOHNPAUL ISIP |
| ZI | Cleared | 12/12/2023 | DARBY WHIPPLE |
| Low Impact Development (LID) | Cleared | 3/20/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | JEANIE LAM |
| Disturb/Remove Protected Trees | Cleared | 4/11/2024 | ADALBERTO VERA |
Contact Information
| Contractor | Rahban Development; Lic. No.: 1089793-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/21/2024 | Partial Inspection | OSVALDO PARAMO |
| Sewer | 7/3/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/3/2024 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| MERV13>=Rough | 7/29/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/29/2024 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/29/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/2/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/2/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/9/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/9/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 8/13/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/28/2024 | Approved | LILIANA PORTILLO |
| Insulation | 8/28/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/6/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/6/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 9/6/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/1/2024 | Approved | LILIANA PORTILLO |
| Final | 11/1/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/1/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 11/1/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/1/2024 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 11/1/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/1/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 11/1/2024 | Not Required | LILIANA PORTILLO |
| Smoke Detectors | 11/1/2024 | Approved | LILIANA PORTILLO |
| Final | 11/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/21/2025 | OK to Issue CofO | LILIANA PORTILLO |