6442 N NEWCASTLE AVE 91335

Certificate Information: 6442 N NEWCASTLE AVE 91335

Application / Permit
23010-10000-04396
Plan Check / Job No.
B23LA20810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/7/2024
Issuing Office
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2023 APPLICANT
Assigned to Plan Check Engineer 11/6/2023 LUISANGEL VALENZUELA
Corrections Issued 11/7/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/5/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/14/2023 LUISANGEL VALENZUELA
Plan Check Approved 2/29/2024 GURUNATH NESARAJAH
No Progress 2/29/2024 GURUNATH NESARAJAH
Plan Check Approved 2/29/2024 GURUNATH NESARAJAH
No Progress 3/7/2024 GURUNATH NESARAJAH
Plan Check Approved 3/7/2024 GURUNATH NESARAJAH
Issued 3/7/2024 APPLICANT
CofO in Progress 2/13/2025 ARUTYUN MADATYAN
Permit Finaled 3/17/2025 JOHN JANSON
CofO Issued 3/17/2025 JOHN JANSON
Permit Finaled 3/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/7/2023 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/9/2023 BRYAN GODINEZ
Sewer availability Cleared 11/9/2023 BRYAN GODINEZ
Low Impact Development (LID) Cleared 2/14/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/15/2024 BRYAN GODINEZ
Construction near power lines Cleared 2/22/2024 RIDWAN HARDY

Contact Information

Contractor I D B Enterprise Inc; Lic. No.: 1032682-B       ,
Engineer Ramos,, Victor; Lic. No.: NA86568       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/11/2024 Approved JEFFREY BULL
Special/Order Compliance 4/11/2024 Corrections Issued JEFFREY BULL
PLUMBING-Rough 4/19/2024 Partial Approval JEFFREY BULL
ELECTRICAL-Rough 6/18/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Corrections Issued JEFFREY BULL
HVAC-Rough 6/18/2024 Approved JEFFREY BULL
PLUMBING-Rough 6/18/2024 Approved JEFFREY BULL
Deputy Wood Construction 6/20/2024 Conditional Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 7/1/2024 Partial Approval MORRIS JACKSON
Insulation 7/30/2024 Approved JEFFREY BULL
Shower Pan 7/30/2024 Approved JEFFREY BULL
Drywall Nailing 8/7/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 1/27/2025 Not Required ARUTYUN MADATYAN
Smoke Detectors 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/12/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/12/2025 Approved ARUTYUN MADATYAN
Final 2/12/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 2/12/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/12/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 2/12/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 2/12/2025 Approved ARUTYUN MADATYAN