6442 N NEWCASTLE AVE 91335
Certificate Information: 6442 N NEWCASTLE AVE 91335
- Application / Permit
- 23010-10000-04396
- Plan Check / Job No.
- B23LA20810
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/7/2024
- Issuing Office
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/7/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/5/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/14/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/29/2024 | GURUNATH NESARAJAH |
| No Progress | 2/29/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/29/2024 | GURUNATH NESARAJAH |
| No Progress | 3/7/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/7/2024 | GURUNATH NESARAJAH |
| Issued | 3/7/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 3/17/2025 | JOHN JANSON |
| CofO Issued | 3/17/2025 | JOHN JANSON |
| Permit Finaled | 3/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/9/2023 | BRYAN GODINEZ |
| Low Impact Development (LID) | Cleared | 2/14/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/15/2024 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 2/22/2024 | RIDWAN HARDY |
Contact Information
| Contractor | I D B Enterprise Inc; Lic. No.: 1032682-B | , |
| Engineer | Ramos,, Victor; Lic. No.: NA86568 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 4/11/2024 | Corrections Issued | JEFFREY BULL |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 6/18/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Corrections Issued | JEFFREY BULL |
| HVAC-Rough | 6/18/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 6/18/2024 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 6/20/2024 | Conditional Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | MORRIS JACKSON |
| Insulation | 7/30/2024 | Approved | JEFFREY BULL |
| Shower Pan | 7/30/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/7/2024 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 1/27/2025 | Not Required | ARUTYUN MADATYAN |
| Smoke Detectors | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 1/27/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| Final | 2/12/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 2/12/2025 | Approved | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 2/12/2025 | Approved | ARUTYUN MADATYAN |