956 S EUCLID AVE 90023
Certificate Information: 956 S EUCLID AVE 90023
- Application / Permit
- 23010-10000-04374
- Plan Check / Job No.
- B23LA10892
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW 2 CAR DETACHED CARPORT AT REAR OF LOT
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | CARLOS MONTES |
| Corrections Issued | 6/21/2023 | CARLOS MONTES |
| Quality Review Completed | 6/26/2023 | KEN GILL |
| Building Plans Picked Up | 6/27/2023 | APPLICANT |
| Applicant returned to address corrections | 11/1/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 1/30/2024 | CARLOS MONTES |
| Plan Check Approved | 2/22/2024 | MARCELA FRANQUEZ |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 12/24/2024 | FREDDIE RIVERA |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/8/2023 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | KATHERINE MENDOZA |
| GPI Written Notices | Cleared | 1/9/2024 | CARLOS MONTES |
| Low Impact Development (LID) | Cleared | 1/9/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/16/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/26/2024 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/10/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 4/10/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/23/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/23/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 4/23/2024 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 9/12/2024 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 9/12/2024 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 9/12/2024 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 9/12/2024 | Approved | FREDDIE RIVERA |
| Final | 12/24/2024 | OK to Issue CofO | FREDDIE RIVERA |