4271 W AVENUE 40 90065
Certificate Information: 4271 W AVENUE 40 90065
- Application / Permit
- 23010-10000-04351
- Plan Check / Job No.
- B23LA20560
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed 2 story ADU
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- Issued on 12/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | JOE VO |
| Corrections Issued | 12/5/2023 | JOE VO |
| Quality Review Completed | 12/7/2023 | PRANITA SHAH |
| Plan Check Approved | 11/19/2024 | JOE VO |
| Issued | 12/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2023 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2023 | ANTHONY TRAN |
| Grading Pre-Inspection | Cleared | 12/27/2023 | JONATHAN HOM |
| Street Frontage | Cleared | 1/9/2024 | JUSTIN BICOL |
| Street width determination | Cleared | 1/9/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 4/26/2024 | RIDWAN HARDY |
| Supp. Use District POD/CDO/TDO | Cleared | 8/13/2024 | ANDREA MAGANA-WITHERS |
| Sewer availability | Cleared | 8/14/2024 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/4/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/9/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | STEVE MELGAR |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/24/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/7/2025 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/5/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 9/5/2025 | Approved | JEFFREY MEAD |
| MERV13>=Rough | 9/5/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/5/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 9/30/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 9/30/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 9/30/2025 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 9/30/2025 | Approved | DAVID WILLIAMS |
| Insulation | 11/25/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 11/25/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Drywall Nailing | 12/26/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 12/26/2025 | Approved | DAVID WILLIAMS |
| Shower Pan | 12/26/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 6/3/2026 | Corrections Issued | RONNIE MEDINA |
| HVAC-Final | 6/3/2026 | Corrections Issued | RONNIE MEDINA |