4271 W AVENUE 40 90065

Certificate Information: 4271 W AVENUE 40 90065

Application / Permit
23010-10000-04351
Plan Check / Job No.
B23LA20560
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Proposed 2 story ADU
Permit Issued
Issued on 12/6/2024
Issuing Office
Current Status
Issued on 12/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 JOE VO
Corrections Issued 12/5/2023 JOE VO
Quality Review Completed 12/7/2023 PRANITA SHAH
Plan Check Approved 11/19/2024 JOE VO
Issued 12/6/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/22/2023 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 12/1/2023 ANTHONY TRAN
Grading Pre-Inspection Cleared 12/27/2023 JONATHAN HOM
Street Frontage Cleared 1/9/2024 JUSTIN BICOL
Street width determination Cleared 1/9/2024 JUSTIN BICOL
Construction near power lines Cleared 4/26/2024 RIDWAN HARDY
Supp. Use District POD/CDO/TDO Cleared 8/13/2024 ANDREA MAGANA-WITHERS
Sewer availability Cleared 8/14/2024 WALLIE JONG
Hydrant and Access approval Cleared 9/4/2024 KURT CORRAL
Low Impact Development (LID) Cleared 10/9/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 10/17/2024 STEVE MELGAR

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/24/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 3/7/2025 Approved SCOTT FINNILA
Footing/Foundation/Slab 3/7/2025 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 9/5/2025 Approved JEFFREY MEAD
HVAC-Rough 9/5/2025 Approved JEFFREY MEAD
MERV13>=Rough 9/5/2025 Approved JEFFREY MEAD
PLUMBING-Rough 9/5/2025 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 9/30/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Approved DAVID WILLIAMS
Green Building Rough 9/30/2025 Approved DAVID WILLIAMS
HVAC-Rough 9/30/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 9/30/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 9/30/2025 Approved DAVID WILLIAMS
Insulation 11/25/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 11/25/2025 Not Ready for Inspection RONNIE MEDINA
Drywall Nailing 12/26/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 12/26/2025 Approved DAVID WILLIAMS
Shower Pan 12/26/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 6/3/2026 Corrections Issued RONNIE MEDINA
HVAC-Final 6/3/2026 Corrections Issued RONNIE MEDINA