5307 1/2 E TEMPLETON ST 90032
Certificate Information: 5307 1/2 E TEMPLETON ST 90032
- Application / Permit
- 23010-10000-04295
- Plan Check / Job No.
- B23LA20242
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: New Detached ADU (1200 SF) ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Current Status
- Issued on 1/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | KHEDER ALRAZAA |
| Corrections Issued | 11/13/2023 | SUNMIN LEE |
| Quality Review Completed | 11/13/2023 | GARO TELMI |
| Applicant returned to address corrections | 12/18/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 8/19/2024 | SUNMIN LEE |
| Plan Check Approved | 12/13/2024 | KHEDER ALRAZAA |
| Issued | 1/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 3/22/2024 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 5/7/2024 | JUSTIN BICOL |
| GPI Written Notices | Cleared | 8/19/2024 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 8/19/2024 | SUNMIN LEE |
| Low Impact Development (LID) | Cleared | 9/19/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/20/2024 | AMBER CAMPBELL |
Contact Information
| Architect | Wu,, Juan-Lieh John; Lic. No.: C11469 | 412 SOUTH STONEMAN AVENUE ALHAMBRA, CA 91801 |
| Contractor | Potato Construction Inc; Lic. No.: 1003152-B | , |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/4/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/16/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/23/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/23/2025 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 5/30/2025 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/22/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 7/22/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/22/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/24/2025 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 7/24/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/12/2025 | Approved | REGINA MENDEZ |
| Insulation | 8/12/2025 | Corrections Issued | REGINA MENDEZ |
| Interior/Exterior Lathing | 8/12/2025 | Approved | REGINA MENDEZ |
| Insulation | 8/19/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/25/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 9/5/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 9/25/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 9/25/2025 | Approved | REGINA MENDEZ |
| Underground Mechanical | 9/25/2025 | Corrections Issued | REGINA MENDEZ |
| Underground Mechanical | 9/26/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 12/9/2025 | Partial Approval | RONNIE MEDINA |
| Final | 2/18/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV No Gas | LILIANA PORTILLO |
| Service/Power Release | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 2/18/2026 | Approved | LILIANA PORTILLO |
| Final | 3/12/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 3/12/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 3/12/2026 | Not Ready for Inspection | LILIANA PORTILLO |