13568 W LUCCA DR 90272

Certificate Information: 13568 W LUCCA DR 90272

Application / Permit
23010-10000-04280
Plan Check / Job No.
B23LA20181
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERSION OF EXISTING POOL HOUSE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW CA Govt. Code 65852.2(e)(1)(A) No change in floor area, height or dimension of (e) structure
Permit Issued
Issued on 5/2/2024
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2023 APPLICANT
Assigned to Plan Check Engineer 10/27/2023 MOHAMMAD ESMAILI
Corrections Issued 10/27/2023 JAD BASMA
Applicant returned to address corrections 11/29/2023 JAD BASMA
Applicant returned to address corrections 2/6/2024 JAD BASMA
Plan Check Approved 3/7/2024 JAD BASMA
Issued 5/2/2024 APPLICANT
CofO in Progress 7/3/2025 ARAM AVEDISIAN
Permit Finaled 7/8/2025 RICHARD STEINBACH
CofO Issued 7/8/2025 RICHARD STEINBACH
Permit Finaled 7/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/15/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 2/15/2024 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 2/28/2024 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Ceron Construction; Lic. No.: 726195-B       ,

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2024 Approved KEVIN SARGSYAN
Insulation 7/22/2024 Approved EVAN COOPER
Drywall Nailing 8/28/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Approved EVAN COOPER
Drywall Nailing 10/17/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/29/2024 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 10/31/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/13/2025 Corrections Issued BOBBY KEY
Final 6/13/2025 Corrections Issued BOBBY KEY
HVAC-Final 6/13/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 6/13/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Final 7/1/2025 Corrections Issued KEVIN SARGSYAN
Final 7/1/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 7/1/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 7/1/2025 Approved KEVIN SARGSYAN
Smoke Detectors 7/1/2025 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/3/2025 Approved ARAM AVEDISIAN
Final 7/3/2025 OK to Issue CofO ARAM AVEDISIAN