726 N FICKETT ST 90033
Certificate Information: 726 N FICKETT ST 90033
- Application / Permit
- 23010-10000-04251
- Plan Check / Job No.
- B23LA19984
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: convert existing detached garage at rear of lot into ADU per WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 11/27/2023
- Issuing Office
- Current Status
- Issued on 11/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2023 | AUNG SOE |
| Corrections Issued | 11/2/2023 | AUNG SOE |
| Applicant returned to address corrections | 11/14/2023 | DANIEL SMILEY |
| Plan Check Approved | 11/16/2023 | KHUONG TRUONG |
| Issued | 11/27/2023 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 11/6/2023 | RUBEN VASQUEZ |
| Address approval | Cleared | 11/7/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 11/7/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 11/14/2023 | DANIEL SMILEY |
Contact Information
| Architect | Juan, Antonio Gutierrez; Lic. No.: C33231 | 15622 PATRONELLA AVENUE GARDENA, CA 90249 |
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/29/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 1/29/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/29/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/29/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 1/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/1/2024 | Approved | OSVALDO PARAMO |
| Sewer | 2/1/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 2/1/2024 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/7/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 2/7/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 2/8/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/15/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 2/15/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/15/2024 | Partial Approval | OSVALDO PARAMO |
| Insulation | 2/20/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 2/26/2024 | Approved | OSVALDO PARAMO |
| Final | 4/19/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 4/19/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 4/19/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 6/5/2025 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 6/5/2025 | Approved | OSVALDO PARAMO |
| Final | 6/10/2025 | Conditional Approval | OSVALDO PARAMO |
| Final | 6/11/2025 | Conditional Approval | ALIZAH MAYAGOITIA |