1841 W 43RD ST 90062
Certificate Information: 1841 W 43RD ST 90062
- Application / Permit
- 23010-10000-04227
- Plan Check / Job No.
- B23LA19848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***eplan*** Add New two story ADU to (E) one Story Garage. LAMC12.22A23(s) -(d).
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- Issued on 10/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | TSE MING HUANG |
| Corrections Issued | 11/6/2023 | TSE MING HUANG |
| Quality Review Completed | 11/6/2023 | EUGENE BARBEAU |
| Plan Check Approved | 10/15/2024 | TSE MING HUANG |
| Issued | 10/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2023 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | ANTHONY TRAN |
| Sewer availability | Cleared | 11/20/2023 | ANTHONY TRAN |
| Low Impact Development (LID) | Cleared | 5/16/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/16/2024 | JESSICA OPINION |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: NA33143 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/3/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/3/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/5/2025 | Partial Approval | SABAS ALONSO |
| Deputy Reinf. Concrete | 3/10/2025 | Conditional Approval | SABAS ALONSO |
| PLUMBING-Rough | 3/19/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 4/29/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/1/2025 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 5/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Drilled-In Anchors | 5/7/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/8/2025 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 5/15/2025 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/2/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/2/2025 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/6/2025 | Partial Approval | JOSE MACIAS |
| HVAC-Rough | 6/6/2025 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 6/6/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/10/2025 | Partial Approval | SABAS ALONSO |
| Shower Pan | 9/10/2025 | Corrections Issued | SABAS ALONSO |
| Insulation | 9/19/2025 | Corrections Issued | RONNIE MEDINA |
| Shower Pan | 9/19/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 1/26/2026 | Approved | SABAS ALONSO |
| Insulation | 1/26/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/26/2026 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 3/16/2026 | Approved | SABAS ALONSO |