4050 N STANSBURY AVE 91423
Certificate Information: 4050 N STANSBURY AVE 91423
- Application / Permit
- 23010-10000-04211
- Plan Check / Job No.
- B23LA19762
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD WITH ATTACHED GARAGE & PATIO COVER & TRELLIS PATIO (2-STORY)
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- CofO Issued on 4/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | CARLOS MONTES |
| Corrections Issued | 11/7/2023 | CARLOS MONTES |
| Quality Review Completed | 11/13/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/1/2024 | CARLOS MONTES |
| Plan Check Approved | 4/18/2024 | CARLOS MONTES |
| Issued | 5/15/2024 | APPLICANT |
| CofO in Progress | 4/14/2026 | MISAEL ESPARZA |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
| CofO Issued | 4/29/2026 | RUBEN SALAS |
| Permit Finaled | 4/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/27/2023 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 12/28/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/28/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 1/24/2024 | MELINEH AGHAKHABIAN |
| Miscellaneous | Cleared | 1/25/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/17/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 4/18/2024 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 4/18/2024 | CARLOS MONTES |
Contact Information
| Architect | Herrera,, David; Lic. No.: NA35011 | , |
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
| Engineer | Hariya,, Manoj; Lic. No.: C74429 | 26121 WALLACK PLACE LOMA LINDA, CA 92354 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/23/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 7/25/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Wood Construction | 8/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 8/12/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/11/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 11/26/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/4/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/4/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/9/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/9/2024 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 12/11/2024 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 12/12/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/16/2024 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 12/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/16/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/16/2024 | Partial Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/16/2024 | Approved | MISAEL ESPARZA |
| Insulation | 12/23/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/23/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/9/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/19/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/19/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/19/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/19/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/19/2026 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/19/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/13/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | MISAEL ESPARZA |
| Final | 3/25/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/25/2026 | Approved | MISAEL ESPARZA |
| Service/Power Release | 3/25/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/2/2026 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 4/2/2026 | Not Ready for Inspection | RAUL OLAGI |
| Final | 4/9/2026 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 4/9/2026 | Approved | MISAEL ESPARZA |