610 N HARVARD BLVD 90004
Certificate Information: 610 N HARVARD BLVD 90004
- Application / Permit
- 23010-10000-04194
- Plan Check / Job No.
- B23LA17881
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN New 3-story SFD w/attached 1-Car Garage (Middle Lot) -BLD SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- CofO Issued on 7/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/18/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/18/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/9/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/23/2024 | MAHNAZ NOURHASHEMI |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | JEFFREY MEAD |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
| CofO Issued | 7/16/2025 | DEROLD HAUFF |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 11/1/2023 | DALIA MOKAYED |
| Address approval | Cleared | 11/7/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 11/9/2023 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 11/16/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 1/27/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/7/2024 | CHRISTINA BRACO |
| SB8 RUD | Cleared | 7/9/2024 | BLAKE BOULIGNY |
Contact Information
| Contractor | Mirageco Construction Inc; Lic. No.: 707777-B | , |
| Engineer | Sandoval,, Martin; Lic. No.: NA56905 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/6/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/7/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 1/7/2025 | Approved | JEFFREY MEAD |
| Deputy Reinf. Concrete | 1/9/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 3/10/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/10/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 3/10/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/12/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 3/12/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 3/12/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Wood Frame | 3/12/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 3/17/2025 | Approved | JEFFREY MEAD |
| Insulation | 3/19/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 3/24/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 4/24/2025 | Approved | BRENDAN MORELLI |
| Sewer | 4/24/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 4/24/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 5/19/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 5/29/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 5/29/2025 | Approved | JEFFREY MEAD |
| Final | 5/30/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 5/30/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 5/30/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Not Required | JEFFREY MEAD |
| Smoke Detectors | 5/30/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 6/2/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 6/2/2025 | Approved | JEFFREY MEAD |
| Final | 6/25/2025 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 6/25/2025 | Approved | JEFFREY MEAD |