872 W Q ST 90744

Certificate Information: 872 W Q ST 90744

Application / Permit
23010-10000-04191
Plan Check / Job No.
B23LA19675
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ADU: 2 BEDROOM, 1 BATHROOM, KITCHEN/LAUNDRY
Permit Issued
Issued on 10/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2023 APPLICANT
Assigned to Plan Check Engineer 11/2/2023 SUNMIN LEE
Corrections Issued 11/9/2023 SUNMIN LEE
Quality Review Completed 11/17/2023 KEN GILL
Building Plans Picked Up 11/27/2023 APPLICANT
Applicant returned to address corrections 10/11/2024 SUNMIN LEE
Plan Check Approved 10/21/2024 SUNMIN LEE
Issued 10/28/2024 APPLICANT
CofO in Progress 11/17/2025 EUGENE CASSIDY
Permit Finaled 11/19/2025 ANSON MAGLASANG
CofO Issued 11/19/2025 ANSON MAGLASANG
Permit Finaled 11/19/2025 ANSON MAGLASANG

Permit Application Clearance Information

Clean Up Green Up Cleared 3/26/2024 NATHAN ROMINE
ZA Case Cleared 3/26/2024 NATHAN ROMINE
ZA Case Cleared 3/26/2024 NATHAN ROMINE
ZI Cleared 3/26/2024 NATHAN ROMINE
Address approval Cleared 4/8/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 4/19/2024 ERIK BEASLEY
Sewer availability Cleared 4/19/2024 ERIK BEASLEY
Low Impact Development (LID) Cleared 9/28/2024 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/3/2024 XOCHITL ARQUIETA

Contact Information

Contractor Muhl Richard T Construction; Lic. No.: 778264-B 10960 BLUFFSIDE DRIVE #102      STUDIO CITY, CA 91604
Engineer Carrillo,, Rene; Lic. No.: C83330 11027 EL REY DR      WHITTIER, CA 90606
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2024 Partial Approval EUGENE CASSIDY
Sewer 12/18/2024 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/24/2024 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/30/2024 Corrections Issued JOSEPH MCGARRY
Deputy Methane Barrier 1/8/2025 Partial Approval EUGENE CASSIDY
METHANE-Subgrade 1/9/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 1/9/2025 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 1/10/2025 Partial Approval EUGENE CASSIDY
METHANE-Barrier 1/15/2025 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 1/21/2025 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 4/2/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 4/2/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 4/2/2025 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/2/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/30/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 4/30/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/19/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/19/2025 Approved EUGENE CASSIDY
Green Building Rough 5/19/2025 Approved EUGENE CASSIDY
HVAC-Rough 5/19/2025 Approved EUGENE CASSIDY
METHANE-Rough 5/19/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 5/19/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/27/2025 Partial Approval EUGENE CASSIDY
Insulation 5/28/2025 Approved EUGENE CASSIDY
Drywall Nailing 6/3/2025 Approved EUGENE CASSIDY
Shower Pan 6/10/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
Final 9/16/2025 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/16/2025 Approved EUGENE CASSIDY
Green Building Final 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 9/16/2025 Approved EUGENE CASSIDY
PLUMBING-Final 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved EUGENE CASSIDY
Service/Power Release 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 9/16/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 10/1/2025 Approved EUGENE CASSIDY
Final 10/1/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 10/1/2025 Approved EUGENE CASSIDY
HVAC-Final 10/1/2025 Approved EUGENE CASSIDY
PLUMBING-Final 10/1/2025 Approved EUGENE CASSIDY
Service/Power Release 10/1/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 10/1/2025 Approved EUGENE CASSIDY
Final 10/28/2025 Not Ready for Inspection ANSON MAGLASANG
Service/Power Release 10/28/2025 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Final 11/12/2025 Approved EUGENE CASSIDY
Final 11/12/2025 Corrections Issued EUGENE CASSIDY
HVAC-Final 11/12/2025 Approved EUGENE CASSIDY
PLUMBING-Final 11/12/2025 Approved EUGENE CASSIDY
Service/Power Release 11/12/2025 Not Required EUGENE CASSIDY
Final 11/17/2025 OK to Issue CofO EUGENE CASSIDY