20401 W VENTURA BLVD 91364
Certificate Information: 20401 W VENTURA BLVD 91364
- Application / Permit
- 23010-10000-04176
- Plan Check / Job No.
- B23LA19593
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- PROPOSED 3 STORY TYPE II-B STORAGE / RETAIL BUILDING WITH 2 LEVELS OF BASEMENT. 1 OF 5
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Zoning Architect | 10/26/2023 | JASON BRAVO |
| Assigned to Plan Check Engineer | 11/2/2023 | JOE VO |
| Corrections Issued | 11/14/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 11/30/2023 | KEN GILL |
| Building Plans Picked Up | 12/5/2023 | APPLICANT |
| Applicant returned to address corrections | 1/26/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/9/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/27/2024 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/18/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 4/10/2025 | JOE VO |
| Issued | 4/16/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2024 | CARLOS AGUILERA |
| Highway dedication | Cleared | 6/8/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/12/2024 | CARLOS RAMIREZ |
| Green Code | Cleared | 7/23/2024 | MICHAEL LOPEZ |
| Driveway location | Cleared | 7/29/2024 | SHEILA AHORAIAN |
| Specific Plan | Cleared | 7/29/2024 | SHEILA AHORAIAN |
| Disturb/Remove Protected Trees | Cleared | 8/15/2024 | MIGUEL ORNELAS |
| Trees in Parkway | Cleared | 8/15/2024 | MIGUEL ORNELAS |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/13/2024 | DANIEL CORONADO |
| GPI Written Notices | Cleared | 9/18/2024 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 9/18/2024 | ROBERT PINA |
| Work Adjacent to Public Way | Cleared | 10/4/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 10/23/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/25/2024 | RYAN CASTRO |
| Building over 36-ft | Cleared | 11/13/2024 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 12/5/2024 | ELIZABETH TOMS |
| Hydrant and Access approval | Cleared | 1/31/2025 | JOHN CONNEALLY |
| Permit | Cleared | 2/28/2025 | RYAN CASTRO |
| "D" conditions | Cleared | 3/10/2025 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 3/10/2025 | DANIEL CORONADO |
| Prkng lot landscape/Water mgmt | Cleared | 3/10/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/10/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 3/11/2025 | DANIEL CORONADO |
| Zoning Plan Check | Cleared | 3/27/2025 | MICHAEL LOPEZ |
Contact Information
| Architect | Michalek,, Christopher; Lic. No.: C38780 | 444 N MICHIGAN AVE #1850 CHICAGO, IL 60611 |
| Contractor | Hbi Commercial Construction Inc; Lic. No.: 1104671-B | 4921 BIRCH STREET SUITE 1 NEWPORT BEACH, CA 92660 |
| Engineer | Johnson,, Steven; Lic. No.: C83319 | 760 MILL ST SILVERTON, OR 97831 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
| Engineer | Zadoorian,, Christopher John; Lic. No.: GE2493 | 1431 MONTGOMEERY ST TUSTIN, CA 92782 |
| Geologist | Wilkins,, Shaun Hunter; Lic. No.: EG2665 | 1716 N GLENVIEW AVE ANAHEIM HILLS, CA 92807 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Excavation/Setback/Form/Re-Bar | 7/23/2026 Time Frame: 10-12 |
| Deputy Drilled-In Anchors | 7/23/2026 |
Inspection Request History
| Special/Order Compliance | 5/20/2025 | Partial Inspection | ROBERT DAVIS |
| Deputy Steel/Welding | 7/18/2025 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 9/11/2025 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 9/17/2025 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 11/17/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 11/18/2025 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 11/19/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 11/24/2025 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 12/4/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Shotcrete | 12/12/2025 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 12/18/2025 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 1/9/2026 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 1/9/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/14/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/15/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/16/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/20/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/26/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/27/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/28/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/29/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 1/30/2026 | Approved | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 1/30/2026 | Partial Inspection | ROBERT DAVIS |
| Deputy Shotcrete | 2/2/2026 | Approved | ROBERT DAVIS |
| Deputy Shotcrete | 2/3/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 2/3/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Shotcrete | 2/5/2026 | Conditional Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 2/5/2026 | Partial Inspection | ROBERT DAVIS |
| Deputy Shotcrete | 2/6/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 2/9/2026 | Conditional Approval | JEFFREY DURAN |
| Deputy Shotcrete | 2/10/2026 | Approved | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 2/10/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Shotcrete | 2/11/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 2/12/2026 | Approved | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Shotcrete | 2/13/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 2/23/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 2/25/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 2/26/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 2/27/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 3/3/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/3/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 3/4/2026 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 3/4/2026 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 3/4/2026 | Partial Approval | GREGORY POMISH |
| Deputy Drilled-In Anchors | 3/5/2026 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 3/5/2026 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 3/6/2026 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Masonry | 3/6/2026 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Masonry | 3/9/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/11/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/12/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/13/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/17/2026 | Approved | ROBERT DAVIS |
| Masonry Wall/Backfill | 3/17/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/18/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/19/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/20/2026 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 3/20/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 3/24/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/24/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/26/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 3/31/2026 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 4/1/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/9/2026 | Approved | ROBERT DAVIS |
| Masonry Wall/Backfill | 4/9/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/10/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/16/2026 | Conditional Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 4/16/2026 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Masonry | 4/17/2026 | Conditional Approval | JOHN KITCKO |
| Structural Steel Frame | 4/21/2026 | Partial Approval | ROBERT DAVIS |
| Wall Anchors | 4/21/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/23/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/23/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/23/2026 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 4/24/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/29/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/29/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 5/1/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/1/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 5/4/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/5/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 5/6/2026 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 5/6/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/8/2026 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 5/8/2026 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/20/2026 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 5/20/2026 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 5/26/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/27/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 6/3/2026 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 6/3/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/4/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 6/5/2026 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 6/5/2026 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 6/15/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 6/16/2026 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 6/23/2026 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 6/23/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/24/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 6/24/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 6/24/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 6/25/2026 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 6/25/2026 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/26/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 7/1/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 7/1/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 7/2/2026 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 7/6/2026 | Partial Approval | ROBERT DAVIS |
| Reinforced Masonry Frame | 7/6/2026 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 7/9/2026 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 7/9/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/10/2026 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 7/13/2026 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 7/13/2026 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 7/16/2026 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 7/16/2026 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 7/21/2026 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 7/21/2026 | Partial Approval | BRIAN KELLY |