4115-4119 N SHADYGLADE AVE 91604
Certificate Information: 4115-4119 N SHADYGLADE AVE 91604
- Application / Permit
- 23010-10000-04158
- Plan Check / Job No.
- B23LA19480
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Proposed 2 story SFD with ATTACHED ADU AND ATTACHED GARAGE ADU CHECKED PER LAMC 12.22 A.33 (C) AND (E)
- Permit Issued
- Issued on 4/25/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2023 | SUNMIN LEE |
| Corrections Issued | 11/7/2023 | SUNMIN LEE |
| Quality Review Completed | 11/8/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/16/2024 | SUNMIN LEE |
| Plan Check Approved | 4/23/2024 | SUNMIN LEE |
| Issued | 4/25/2024 | APPLICANT |
| CofO in Progress | 7/21/2025 | JUAN VALENZUELA |
| Permit Finaled | 7/21/2025 | RUBEN SALAS |
| CofO Issued | 7/21/2025 | RUBEN SALAS |
| Permit Finaled | 7/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 1/23/2024 | COLIN LOREDO |
| ZI | Cleared | 2/13/2024 | ASHLEY RODARTE |
| Hydrant and Access approval | Cleared | 3/1/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 3/19/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/7/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/9/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 5/9/2024 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/23/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 5/23/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/11/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/11/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 7/11/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/1/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/1/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/9/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/9/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | JACK KARGODORIAN |
| Insulation | 8/15/2024 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/26/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 8/29/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 9/10/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/12/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/3/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 4/15/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 4/15/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/18/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 4/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 4/18/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/21/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/21/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/22/2025 | Approved | CHRISTOPHE COCHRAN |
| Special/Order Compliance | 4/22/2025 | Partial Inspection | JUAN VALENZUELA |
| Insulation | 4/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/8/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 5/8/2025 | Approved | CHRISTOPHE COCHRAN |
| Reinforced Concrete Frame | 5/8/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/8/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/8/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 5/19/2025 | Partial Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/19/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Order to Comply | 6/18/2025 | OTC Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 7/7/2025 | Partial Approval | JACK KARGODORIAN |
| Pre-Inspection | 7/9/2025 | Approved | JUAN VALENZUELA |
| Final | 7/21/2025 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 7/21/2025 | Approved | JUAN VALENZUELA |