3218 1/2 W 60TH ST 90043
Certificate Information: 3218 1/2 W 60TH ST 90043
- Application / Permit
- 23010-10000-04155
- Plan Check / Job No.
- B23LA19464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan :CONVERSION OF EXISTING DETACHED GARAGE INTO ADU PER STATE LAW AND GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/27/2024
- Issuing Office
- Current Status
- CofO Issued on 9/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2023 | ZAW HAN |
| Corrections Issued | 10/19/2023 | ZAW HAN |
| Applicant returned to address corrections | 11/14/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 11/20/2023 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 12/5/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 12/20/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 1/22/2024 | JOSEPH RAFOLS |
| No Progress | 1/26/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 1/26/2024 | JOSEPH RAFOLS |
| Issued | 1/27/2024 | APPLICANT |
| CofO in Progress | 9/11/2024 | AMIR NAZARIAN |
| Permit Finaled | 9/11/2024 | RUBEN SALAS |
| CofO Issued | 9/11/2024 | RUBEN SALAS |
| Permit Finaled | 9/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2023 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/13/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2023 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 1/18/2024 | OSCAR CASTRO |
Contact Information
| Contractor | Bridgeline Construction; Lic. No.: 1078101-B | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: NA5524 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/30/2024 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 2/15/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/22/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 2/27/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 2/27/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 2/27/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 3/15/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 3/18/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 3/18/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 3/18/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/18/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/21/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 3/21/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 3/21/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 3/21/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/21/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/26/2024 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 3/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 3/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/28/2024 | Conditional Approval | JOSE MACIAS |
| ELECTRICAL-Rough | 3/28/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 3/28/2024 | Conditional Approval | JOSE MACIAS |
| PLUMBING-Rough | 3/28/2024 | Conditional Approval | JOSE MACIAS |
| Insulation | 4/1/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 4/1/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 4/4/2024 | Conditional Approval | JOSE MACIAS |
| Underground Mechanical | 4/9/2024 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 4/17/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | JOSE MACIAS |
| Final | 5/28/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 5/28/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 5/28/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 5/28/2024 | Approved | JOSE MACIAS |
| Final | 6/20/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 6/20/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | JOSE MACIAS |
| ELECTRICAL-Final | 6/24/2024 | Approved | JOSE MACIAS |
| Final | 6/24/2024 | Conditional Approval | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | JOSE MACIAS |
| Final | 9/10/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/11/2024 | OK to Issue CofO | AMIR NAZARIAN |