330-330 1/2 E 99TH ST 90003
Certificate Information: 330-330 1/2 E 99TH ST 90003
- Application / Permit
- 23010-10000-04148
- Plan Check / Job No.
- B23LA19442
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE NFPA 13D REQUIRED THROUGH OUT
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | JAD BASMA |
| Assigned to Zoning Architect | 10/19/2023 | BENNY WONG |
| Corrections Issued | 10/21/2023 | JAD BASMA |
| Quality Review Completed | 10/24/2023 | PRANITA SHAH |
| Applicant returned to address corrections | 3/6/2024 | JAD BASMA |
| Applicant returned to address corrections | 3/12/2024 | JAD BASMA |
| Plan Check Approved | 3/12/2024 | JAD BASMA |
| No Progress | 3/12/2024 | JAD BASMA |
| Plan Check Approved | 4/26/2024 | JAD BASMA |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 10/29/2024 | BEN MOLSTAD |
| Permit Finaled | 11/1/2024 | ANSON MAGLASANG |
| CofO Issued | 11/1/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/1/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2023 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 11/16/2023 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 11/22/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 11/28/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | TREVOR QUAN |
| SB8 RUD | Cleared | 2/5/2024 | PATRICIA ALFARO |
| Frnt yard landscape/Water mgmt | Cleared | 2/14/2024 | GEORGIA SMITH |
| ZI | Cleared | 2/14/2024 | GEORGIA SMITH |
| Miscellaneous | Cleared | 4/23/2024 | NOAH MCCOY |
| Zoning Plan Check | Cleared | 4/25/2024 | Lawrence Quirante |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2024 | Approved | BEN MOLSTAD |
| Underground Mechanical | 6/21/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 6/21/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 6/24/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 8/14/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 8/14/2024 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 8/15/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 8/16/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 8/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 8/19/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 8/19/2024 | Partial Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 8/20/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 8/20/2024 | Partial Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 8/20/2024 | Approved | BEN MOLSTAD |
| Insulation | 8/21/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 8/21/2024 | Partial Inspection | BARRY HACHE |
| Insulation | 8/23/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 8/26/2024 | Not Ready for Inspection | BARRY HACHE |
| Special/Order Compliance | 8/26/2024 | Partial Inspection | BEN MOLSTAD |
| Drywall Nailing | 8/30/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 8/30/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 10/11/2024 | Approved | BARRY HACHE |
| HVAC-Final | 10/24/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/24/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/25/2024 | Approved | ANTHONY EGSON |
| Final | 10/25/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Final | 10/25/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2024 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 10/25/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 10/25/2024 | Approved | ANTHONY EGSON |
| Final | 10/29/2024 | OK to Issue CofO | BEN MOLSTAD |
| Special/Order Compliance | 10/29/2024 | Approved | BEN MOLSTAD |