943 N STONEHILL LANE 90049
Certificate Information: 943 N STONEHILL LANE 90049
- Application / Permit
- 23010-10000-04137
- Plan Check / Job No.
- B23LA19368
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY BUILDING, GARAGE LOCATED BELOW AND DETACHED ADU ABOVE PER DETACHED ADU PER LAMC 12.22 A.33(c)(4) (2-STORY)
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- Current Status
- Issued on 1/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | CARLOS MONTES |
| Corrections Issued | 11/15/2023 | CARLOS MONTES |
| Quality Review Completed | 11/16/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/18/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 8/6/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 12/12/2024 | CARLOS MONTES |
| Plan Check Approved | 1/27/2025 | CARLOS MONTES |
| Issued | 1/27/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/17/2024 | EDGAR PASCUA |
| Street Frontage | Cleared | 1/17/2024 | DARIN LAM |
| Address approval | Cleared | 1/18/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/18/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 2/17/2024 | JOHN CONNEALLY |
| Private street | Cleared | 12/11/2024 | ALEX VELA |
| Excavation more than 5-ft deep | Cleared | 12/13/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 12/13/2024 | ROBERT PINA |
| Grading Pre-Inspection | Cleared | 12/13/2024 | CARLOS MONTES |
| Miscellaneous | Cleared | 12/23/2024 | NELSON RODRIGUEZ |
| Low Impact Development (LID) | Cleared | 1/15/2025 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Lind,, Eric Christopher; Lic. No.: NA16909 | , |
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Ramon; Lic. No.: NA4595 | , |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Engineer | Vardeh,, Edmond; Lic. No.: C56992 | 43 INVERARY TRABUCO CANYON, CA 92679 |
| Geologist | Hogrefe,, Scott Joseph; Lic. No.: EG1516 | 3157 ESCOLLERA AVE SANTA ROSA VALLEY, CA 93012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/10/2025 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 7/24/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/15/2025 | Approved | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 8/15/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/20/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 8/28/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 8/28/2025 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Shotcrete | 9/3/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 9/9/2025 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/11/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 9/11/2025 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/16/2025 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 9/25/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 10/24/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Reinf. Masonry | 11/6/2025 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/7/2025 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 11/12/2025 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/16/2025 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/16/2025 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 12/22/2025 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/23/2025 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/26/2026 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/26/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 1/27/2026 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 2/4/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 2/4/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 2/5/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/5/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/13/2026 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 3/5/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/5/2026 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/10/2026 | Partial Approval | KEVIN SARGSYAN |
| Reinforced Masonry Frame | 4/10/2026 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 4/28/2026 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/15/2026 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 5/15/2026 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 6/30/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/8/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2026 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 7/13/2026 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 7/17/2026 | Not Ready for Inspection | KEVIN SARGSYAN |