420 S BRISTOL AVE 90049

Certificate Information: 420 S BRISTOL AVE 90049

Application / Permit
23010-10000-04130
Plan Check / Job No.
B23LA19348
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
EPLAN: NEW 223 SF IRREGULAR SHAPED POOL HOUSE WITH NEW BATHROOM, STORAGE, AND ATTACHED 350 SF TRELLIS. RELOCATE POOL EQUIPMENT. ALL WORK PER ENG.
Permit Issued
Issued on 11/14/2024
Issuing Office
Current Status
Issued on 11/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/16/2023 APPLICANT
Assigned to Plan Check Engineer 10/18/2023 GIOVANNY CHAVEZ
Corrections Issued 10/19/2023 GIOVANNY CHAVEZ
Applicant returned to address corrections 11/15/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/28/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/29/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/6/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/24/2024 GIOVANNY CHAVEZ
Plan Check Approved 11/14/2024 GIOVANNY CHAVEZ
Issued 11/14/2024 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 9/6/2024 DALIA MOKAYED
Eng Process Fee Ord 176,300 Cleared 9/8/2024 BRENDEN HAWK
Specific Plan Cleared 9/12/2024 PEDRO AYALA
Grading Pre-Inspection Cleared 9/24/2024 GIOVANNY CHAVEZ
Low Impact Development (LID) Cleared 11/7/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 11/8/2024 ANTHONY MAINEZ

Contact Information

Architect Zahabian,, Philip; Lic. No.: C23813 5237 NEWCASTLE AVE #307      ENCINO, CA 91316
Contractor Owner-Builder       ,
Engineer Taubman,, David; Lic. No.: S1445 1412 ALLENFORD AVE      LOS ANGELES, CA 90049

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 11/26/2024 Corrections Issued JESUS RODRIGUEZ
Gas Test 12/3/2024 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 12/4/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 1/27/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 1/27/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/27/2025 Approved JESUS RODRIGUEZ
Insulation 2/4/2025 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 2/4/2025 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 2/5/2025 Approved JESUS RODRIGUEZ
Green Building Rough 2/5/2025 Approved JESUS RODRIGUEZ
Insulation 2/5/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 3/17/2025 Approved KEVIN SARGSYAN
Grounding or Bonding 4/29/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/30/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/30/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 12/30/2025 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready KEVIN SARGSYAN
ELECTRICAL-Final 4/6/2026 Corrections Issued KEVIN SARGSYAN
HVAC-Final 4/6/2026 Approved KEVIN SARGSYAN
PLUMBING-Final 4/6/2026 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/6/2026 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 4/6/2026 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/13/2026 Not Ready for Inspection DANIEL VERA
Final 4/13/2026 Not Ready for Inspection DANIEL VERA
Green Building Final 4/13/2026 Approved DANIEL VERA
HVAC-Final 4/13/2026 Approved DANIEL VERA
PLUMBING-Final 4/13/2026 Approved DANIEL VERA