4716 S 2ND AVE 90043
Certificate Information: 4716 S 2ND AVE 90043
- Application / Permit
- 23010-10000-04091
- Plan Check / Job No.
- B23LA19128
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE AND REC ROOM PER LAMC 12.22A.33(c)-(d). SOLAR INSTALLATION TO MEET 2.46KW PER TITLE 24 REQUIRED PRIOR TO COFO.
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 6/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | VIVIAN LAO |
| Corrections Issued | 10/20/2023 | VIVIAN LAO |
| Quality Review Completed | 10/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/24/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 6/11/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 7/2/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 7/11/2024 | VIVIAN LAO |
| Plan Check Approved | 7/12/2024 | VIVIAN LAO |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 5/16/2025 | LUIS CASTRO |
| No Progress | 5/18/2025 | DEROLD HAUFF |
| CofO in Progress | 5/18/2025 | DEROLD HAUFF |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
| CofO Issued | 6/22/2025 | DEROLD HAUFF |
| Permit Finaled | 6/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 2/26/2024 | TREVOR QUAN |
| Low Impact Development (LID) | Cleared | 4/30/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/17/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Dunsmuir Associates; Lic. No.: 782018-B | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: NA5524 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/4/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/10/2024 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 10/9/2024 | Conditional Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 1/7/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 1/7/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/13/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 1/13/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 1/13/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 1/13/2025 | Corrections Issued | LUIS CASTRO |
| Verify Sprinkler Sign Off | 1/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 1/15/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/16/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 1/16/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/24/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 1/31/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/5/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 2/5/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/5/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/5/2025 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 2/5/2025 | Corrections Issued | JUSTIN HAWLEY |
| Sewer | 3/10/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 3/12/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 3/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 4/16/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 4/16/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/16/2025 | Corrections Issued | LUIS CASTRO |
| Special/Order Compliance | 4/16/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 4/23/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Final | 4/23/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/30/2025 | Approved | LUIS CASTRO |
| Green Building Final | 4/30/2025 | Approved | LUIS CASTRO |
| Final | 5/5/2025 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Required | LUIS CASTRO |
| Service/Power Release | 5/5/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 5/5/2025 | Approved | LUIS CASTRO |
| Final | 5/16/2025 | OK to Issue CofO | LUIS CASTRO |