4716 S 2ND AVE 90043

Certificate Information: 4716 S 2ND AVE 90043

Application / Permit
23010-10000-04091
Plan Check / Job No.
B23LA19128
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE AND REC ROOM PER LAMC 12.22A.33(c)-(d). SOLAR INSTALLATION TO MEET 2.46KW PER TITLE 24 REQUIRED PRIOR TO COFO.
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
CofO Issued on 6/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2023 APPLICANT
Assigned to Plan Check Engineer 10/19/2023 VIVIAN LAO
Corrections Issued 10/20/2023 VIVIAN LAO
Quality Review Completed 10/20/2023 GARO TELMI
Applicant returned to address corrections 5/24/2024 VIVIAN LAO
Applicant returned to address corrections 6/11/2024 VIVIAN LAO
Applicant returned to address corrections 7/2/2024 VIVIAN LAO
Applicant returned to address corrections 7/11/2024 VIVIAN LAO
Plan Check Approved 7/12/2024 VIVIAN LAO
Issued 7/16/2024 APPLICANT
CofO in Progress 5/16/2025 LUIS CASTRO
No Progress 5/18/2025 DEROLD HAUFF
CofO in Progress 5/18/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF
CofO Issued 6/22/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/23/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/26/2024 TREVOR QUAN
Sewer availability Cleared 2/26/2024 TREVOR QUAN
Low Impact Development (LID) Cleared 4/30/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/17/2024 JUSTIN BICOL

Contact Information

Contractor Dunsmuir Associates; Lic. No.: 782018-B       ,
Engineer Cooke,, Conway Cecil; Lic. No.: NA5524       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/28/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 9/4/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/4/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 9/10/2024 Approved ANTHONY EGSON
Deputy Wood Construction 10/9/2024 Conditional Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 1/7/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval LUIS CASTRO
HVAC-Rough 1/7/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 1/7/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 1/13/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 1/13/2025 Approved LUIS CASTRO
Green Building Rough 1/13/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 1/13/2025 Corrections Issued LUIS CASTRO
Verify Sprinkler Sign Off 1/13/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved LUIS CASTRO
HVAC-Rough 1/15/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 1/16/2025 Partial Approval LUIS CASTRO
HVAC-Rough 1/16/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 1/24/2025 Partial Approval ANTHONY RAMOS
Insulation 1/31/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/5/2025 Approved JUSTIN HAWLEY
Drywall Nailing 2/5/2025 Approved JUSTIN HAWLEY
Green Building Rough 2/5/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/5/2025 Approved JUSTIN HAWLEY
Special/Order Compliance 2/5/2025 Corrections Issued JUSTIN HAWLEY
Sewer 3/10/2025 Approved LUIS CASTRO
Underground Mechanical 3/12/2025 Approved LUIS CASTRO
PLUMBING-Final 3/26/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 4/16/2025 Corrections Issued LUIS CASTRO
HVAC-Final 4/16/2025 Approved LUIS CASTRO
PLUMBING-Final 4/16/2025 Corrections Issued LUIS CASTRO
Special/Order Compliance 4/16/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Final 4/23/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 4/23/2025 Approved LUIS CASTRO
ELECTRICAL-Final 4/30/2025 Approved LUIS CASTRO
Green Building Final 4/30/2025 Approved LUIS CASTRO
Final 5/5/2025 Corrections Issued LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Not Required LUIS CASTRO
Service/Power Release 5/5/2025 Approved LUIS CASTRO
Smoke Detectors 5/5/2025 Approved LUIS CASTRO
Final 5/16/2025 OK to Issue CofO LUIS CASTRO