10410 S MCKINLEY AVE 90002
Certificate Information: 10410 S MCKINLEY AVE 90002
- Application / Permit
- 23010-10000-04080
- Plan Check / Job No.
- B23LA19071
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. PER ORDINANCE AT REAR OF LOT. CONSTRUCTION PER W.F.P.P. ALL ELECTRIC ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/17/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 10/30/2023 | APPLICANT |
| Applicant returned to address corrections | 7/5/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 8/29/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 12/24/2024 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 12/31/2024 | CARLOS MONTES |
| Plan Check Approved | 1/15/2025 | DANIEL SANJUAN |
| Issued | 1/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/22/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 12/17/2024 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/28/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/10/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 3/3/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 3/7/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 5/9/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/9/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 5/9/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/15/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 5/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/23/2025 | Approved | JOHN KLARIN |
| HVAC-Rough | 5/23/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/23/2025 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/9/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 6/9/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/9/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/12/2025 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/12/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | ANTHONY EGSON |
| Insulation | 7/21/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/21/2025 | Approved | ANTHONY EGSON |
| Insulation | 7/28/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/11/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/11/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 8/11/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/27/2025 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 5/8/2026 | Approved | ARTHUR NEGRETE |
| Final | 5/8/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 5/8/2026 | Approved | ARTHUR NEGRETE |
| Green Building Final | 5/8/2026 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 5/8/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 5/8/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 5/8/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 5/8/2026 | Approved | ARTHUR NEGRETE |