1126-1130 N WATSON AVE 90744

Certificate Information: 1126-1130 N WATSON AVE 90744

Application / Permit
23010-10000-04075
Plan Check / Job No.
B23LA19060
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2-STORY addition to existing SFR and convert to a duplex WITH ATTACHED GARAGE. per SB9 1 OF 2
Permit Issued
Issued on 9/4/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 ARSALAN SHABESTARI
Corrections Issued 10/18/2023 ARSALAN SHABESTARI
Quality Review Completed 10/25/2023 FARUK SEZER
Building Plans Picked Up 11/1/2023 APPLICANT
Applicant returned to address corrections 4/25/2024 ARSALAN SHABESTARI
Plan Check Approved 9/3/2024 ARSALAN SHABESTARI
Issued 9/4/2024 APPLICANT
CofO in Progress 8/22/2025 EUGENE CASSIDY
Permit Finaled 8/29/2025 ANSON MAGLASANG
CofO Issued 8/29/2025 ANSON MAGLASANG
Permit Finaled 8/29/2025 ANSON MAGLASANG

Permit Application Clearance Information

Clean Up Green Up Cleared 11/20/2023 MAXFIELD VERMY
ZA Case Cleared 11/20/2023 MAXFIELD VERMY
Address approval Cleared 12/14/2023 ERIK BEASLEY
Permit Cleared 12/14/2023 ERIK BEASLEY
Miscellaneous Cleared 1/23/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 3/7/2024 ERIK BEASLEY
Low Impact Development (LID) Cleared 3/7/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/7/2024 ERIK BEASLEY
Sewer availability Cleared 3/7/2024 ERIK BEASLEY
Abandoned oil well Cleared 4/15/2024 LAVEON RIDER
Hydrant and Access approval Cleared 4/15/2024 LAVEON RIDER
Senate Bill 9 Cleared 5/30/2024 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2024 Partial Approval JOSEPH MCGARRY
METHANE-Subgrade 9/9/2024 Approved JOSEPH MCGARRY
Underground Mechanical 9/9/2024 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/16/2024 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 9/16/2024 Approved JOSEPH MCGARRY
METHANE-Barrier 9/16/2024 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval EUGENE CASSIDY
Sewer 9/24/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval EUGENE CASSIDY
Insulation 9/26/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 10/15/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/7/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/7/2024 Approved EUGENE CASSIDY
Green Building Rough 11/7/2024 Approved EUGENE CASSIDY
HVAC-Rough 11/7/2024 Approved EUGENE CASSIDY
METHANE-Rough 11/7/2024 Approved EUGENE CASSIDY
Insulation 11/12/2024 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 11/12/2024 Conditional Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 11/12/2024 Approved JOSEPH MCGARRY
Drywall Nailing 11/18/2024 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 11/18/2024 Approved JOSEPH MCGARRY
Underground Mechanical 11/18/2024 Partial Approval JOSEPH MCGARRY
Final 7/2/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 7/2/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Required EUGENE CASSIDY
Smoke Detectors 7/2/2025 Approved EUGENE CASSIDY
Final 7/8/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 7/8/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/22/2025 Approved EUGENE CASSIDY
Final 8/22/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/22/2025 Approved EUGENE CASSIDY
PLUMBING-Final 8/22/2025 Approved EUGENE CASSIDY
Service/Power Release 8/22/2025 Approved EUGENE CASSIDY