336-338 S BURLINGAME AVE 90049
Certificate Information: 336-338 S BURLINGAME AVE 90049
- Application / Permit
- 23010-10000-04070
- Plan Check / Job No.
- B23LA19056
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD PER SB9 TWO UNIT DEVELOPMENT WITH ATTACHED ADU PER ORDINANCE (2-STORY) WITH TRELLIS ROOF AND SOLID ROOF PORCH
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | CARLOS MONTES |
| Corrections Issued | 10/16/2023 | CARLOS MONTES |
| Quality Review Completed | 10/16/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/31/2024 | CARLOS MONTES |
| Plan Check Approved | 4/1/2024 | CARLOS MONTES |
| Issued | 4/9/2024 | APPLICANT |
| CofO in Progress | 3/18/2026 | HERBERT GIRON |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Tract Map conditions | Cleared | 11/2/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 11/2/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 11/2/2023 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 12/12/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 12/22/2023 | ROGELIO CORTES |
| Senate Bill 9 | Cleared | 12/22/2023 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 1/16/2024 | MOHAMMAD HASAN |
| GPI Written Notices | Cleared | 1/31/2024 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 1/31/2024 | CARLOS MONTES |
| Sewer availability | Cleared | 2/8/2024 | DARIN LAM |
Contact Information
| Architect | Holz,, Michael B; Lic. No.: C28082 | 12548 EVERGLADE STREET LOS ANGELES, CA 90066 |
| Contractor | M G Partners Inc; Lic. No.: 886387-B | 761 E DAILY DR #140 CAMARILLO, CA 93010 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/8/2024 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 7/19/2024 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 7/24/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/29/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/2/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 9/30/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Sewer | 10/2/2024 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 10/4/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 10/23/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/27/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 1/28/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/4/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/26/2025 | Corrections Issued | HERBERT GIRON |
| Insulation | 3/26/2025 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/7/2025 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 4/7/2025 | Partial Approval | HERBERT GIRON |
| Insulation | 4/7/2025 | Conditional Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 4/7/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/15/2025 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 4/23/2025 | Partial Approval | SEAN HAUPT |
| Shower Pan | 4/23/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 6/23/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Final | 12/11/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 1/13/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/29/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/29/2026 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/3/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 2/3/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | HERBERT GIRON |
| Final | 3/9/2026 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/9/2026 | Approved | HERBERT GIRON |
| Green Building Final | 3/9/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 3/9/2026 | Approved | HERBERT GIRON |
| Final | 3/17/2026 | OK to Issue CofO | HERBERT GIRON |