4708 N NOBLE AVE 91403

Certificate Information: 4708 N NOBLE AVE 91403

Application / Permit
23010-10000-04022
Plan Check / Job No.
B23LA18164
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
eplan NEW REC ROOM AT REAR OF PROPERTY
Permit Issued
Issued on 2/24/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 JAD BASMA
Corrections Issued 10/7/2023 JAD BASMA
Quality Review Completed 10/11/2023 GARO TELMI
Applicant returned to address corrections 1/16/2024 JAD BASMA
Plan Check Approved 2/21/2024 JAD BASMA
Issued 2/24/2024 APPLICANT
CofO in Progress 2/3/2025 JACK KARGODORIAN
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/18/2023 CARLOS AGUILERA
Sewer availability Cleared 10/18/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/19/2023 CARLOS AGUILERA
Construction near power lines Cleared 12/26/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/29/2024 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 4/17/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/17/2024 Approved THOMAS FINNILA
Deputy Reinf. Concrete 4/18/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 5/28/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 5/28/2024 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 5/28/2024 Approved JACK KARGODORIAN
HVAC-Rough 5/28/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/28/2024 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 5/28/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/30/2024 Approved JACK KARGODORIAN
Gas Test 5/30/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/30/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/5/2024 Approved MICHEL ABAJAN
Shower Pan 6/5/2024 Approved MICHEL ABAJAN
Insulation 6/6/2024 Approved GREGG CUMMINGS
Drywall Nailing 6/10/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/10/2024 Approved JACK KARGODORIAN
HVAC-Final 9/5/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 9/5/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 9/9/2024 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 9/9/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 9/10/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/13/2024 Approved JACK KARGODORIAN
Final 9/13/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 9/13/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/13/2024 Not Required JACK KARGODORIAN
Smoke Detectors 9/13/2024 Approved JACK KARGODORIAN
Final 1/30/2025 OK to Issue CofO JACK KARGODORIAN