4708 N NOBLE AVE 91403
Certificate Information: 4708 N NOBLE AVE 91403
- Application / Permit
- 23010-10000-04022
- Plan Check / Job No.
- B23LA18164
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- eplan NEW REC ROOM AT REAR OF PROPERTY
- Permit Issued
- Issued on 2/24/2024
- Issuing Office
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | JAD BASMA |
| Corrections Issued | 10/7/2023 | JAD BASMA |
| Quality Review Completed | 10/11/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/16/2024 | JAD BASMA |
| Plan Check Approved | 2/21/2024 | JAD BASMA |
| Issued | 2/24/2024 | APPLICANT |
| CofO in Progress | 2/3/2025 | JACK KARGODORIAN |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
| CofO Issued | 2/18/2025 | RUBEN SALAS |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/18/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/18/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/26/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/29/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/17/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/17/2024 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/18/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 5/28/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/28/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/30/2024 | Approved | JACK KARGODORIAN |
| Gas Test | 5/30/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/30/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/5/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/5/2024 | Approved | MICHEL ABAJAN |
| Insulation | 6/6/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/10/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/10/2024 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 9/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 9/9/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 9/9/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 9/10/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | JACK KARGODORIAN |
| Final | 9/13/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/13/2024 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 9/13/2024 | Not Required | JACK KARGODORIAN |
| Smoke Detectors | 9/13/2024 | Approved | JACK KARGODORIAN |
| Final | 1/30/2025 | OK to Issue CofO | JACK KARGODORIAN |