5300 N LOUISE AVE 91316

Certificate Information: 5300 N LOUISE AVE 91316

Application / Permit
23010-10000-04014
Plan Check / Job No.
B23LA18740
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New Detached Patio and BBQ island
Permit Issued
Issued on 1/5/2024
Issuing Office
Current Status
Issued on 1/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/10/2023 JOE VO
Corrections Issued 10/10/2023 JOE VO
Applicant returned to address corrections 12/14/2023 DANIEL YIP
Plan Check Approved 1/4/2024 DANIEL YIP
Issued 1/5/2024 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 11/20/2023 STEVEN WECHSLER
ZA Case Cleared 11/20/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 11/29/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 12/29/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/3/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 1/30/2024 Approved JON MCHUGH
Deputy Steel/Welding 4/9/2024 Conditional Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval MORRIS JACKSON
Wood Frame 6/4/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 6/10/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 6/10/2024 Approved JON MCHUGH
PLUMBING-Rough 6/10/2024 Approved JON MCHUGH
Drywall Nailing 6/24/2024 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 6/24/2024 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection JON MCHUGH
Final 9/4/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Approved JON MCHUGH
Service/Power Release 9/4/2024 Not Required JON MCHUGH
Smoke Detectors 9/4/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 9/4/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 8/6/2025 No Access for Inspection MORRIS JACKSON
Final 8/6/2025 No Access for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 3/25/2026 Approved JON MCHUGH
Final 3/25/2026 Not Ready for Inspection JON MCHUGH