1617 S BURNSIDE AVE 90019

Certificate Information: 1617 S BURNSIDE AVE 90019

Application / Permit
23010-10000-04009
Plan Check / Job No.
B23LA18728
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New 1 story 23'x26'detached ADU per WFPP ADU PER STATE LAW CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) ***see comment***
Permit Issued
Issued on 2/22/2024
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/10/2023 AUNG SOE
Corrections Issued 1/11/2024 JAD BASMA
Applicant returned to address corrections 1/25/2024 JAD BASMA
Applicant returned to address corrections 1/31/2024 JAD BASMA
Plan Check Approved 2/6/2024 JAD BASMA
Issued 2/22/2024 APPLICANT
CofO in Progress 8/12/2024 STUART CHAPMAN
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/17/2023 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 10/18/2023 ARNULFO CHAMU
Sewer availability Cleared 10/18/2023 ARNULFO CHAMU
Low Impact Development (LID) Cleared 12/22/2023 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 12/26/2023 ARNULFO CHAMU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/15/2024 No Access for Inspection STUART CHAPMAN
Pre-Inspection 3/15/2024 No Access for Inspection STUART CHAPMAN
Underground Mechanical 3/15/2024 No Access for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/19/2024 Partial Inspection STUART CHAPMAN
Sewer 3/19/2024 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval STUART CHAPMAN
Underground Mechanical 3/21/2024 Approved STUART CHAPMAN
Footing/Foundation/Slab 3/28/2024 Approved STUART CHAPMAN
Deputy Wood Construction 4/10/2024 Partial Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/25/2024 Approved RICHARD DOCKUS
PLUMBING-Rough 4/25/2024 Approved RICHARD DOCKUS
Shower Pan 4/25/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/30/2024 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 4/30/2024 Approved JOAQUIN GREENOUGH
HVAC-Rough 4/30/2024 Conditional Approval JOAQUIN GREENOUGH
Special/Order Compliance 4/30/2024 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/30/2024 Approved JOAQUIN GREENOUGH
Insulation 5/6/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/6/2024 Approved ENRIQUE MIRELES
Drywall Nailing 5/9/2024 Approved AMIR NAZARIAN
Underground Mechanical 6/24/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/8/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/8/2024 Approved ENRIQUE MIRELES
Final 7/8/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/8/2024 Approved ENRIQUE MIRELES
PLUMBING-Final 7/8/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/8/2024 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 7/8/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/22/2024 Approved ARTHUR NEGRETE
HVAC-Final 7/22/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 7/22/2024 Approved ARTHUR NEGRETE
Final 8/12/2024 OK to Issue CofO STUART CHAPMAN
Service/Power Release 8/12/2024 Approved STUART CHAPMAN