5746-5746 1/2 W 85TH PL 90045
Certificate Information: 5746-5746 1/2 W 85TH PL 90045
- Application / Permit
- 23010-10000-03986
- Plan Check / Job No.
- B23LA18553
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached 2 story 2-unit ADU
- Permit Issued
- Issued on 5/18/2024
- Issuing Office
- Current Status
- CofO Issued on 12/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | PRANITA SHAH |
| Corrections Issued | 10/17/2023 | PRANITA SHAH |
| Quality Review Completed | 10/18/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/11/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/19/2024 | PRANITA SHAH |
| Plan Check Approved | 5/17/2024 | PRANITA SHAH |
| Issued | 5/18/2024 | APPLICANT |
| CofO in Progress | 12/9/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 12/10/2024 | RICHARD STEINBACH |
| CofO Issued | 12/10/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/10/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2023 | DINAH GARIN |
| Highway dedication | Cleared | 10/25/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2023 | DINAH GARIN |
| Sewer availability | Cleared | 10/27/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/20/2023 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 12/27/2023 | RIDWAN HARDY |
| Specific Plan | Cleared | 1/30/2024 | JOSHUA JONES |
| Low Impact Development (LID) | Cleared | 2/14/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/28/2024 | DINAH GARIN |
| GPI Written Notices | Cleared | 5/17/2024 | PRANITA SHAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/22/2024 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/30/2024 | Corrections Issued | BOBBY KEY |
| Deputy Drilled-In Anchors | 6/21/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/21/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 7/12/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/2/2024 | Approved | BOBBY KEY |
| Sewer | 8/2/2024 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 8/7/2024 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 8/7/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | BOBBY KEY |
| Green Building Rough | 8/14/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/14/2024 | Partial Approval | BOBBY KEY |
| Insulation | 8/19/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 8/28/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/28/2024 | Approved | BOBBY KEY |
| Green Building Final | 10/31/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 10/31/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Service/Power Release | 10/31/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Smoke Detectors | 10/31/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 11/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 11/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/1/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Required | TEMISTOCLES CAAL |
| Smoke Detectors | 11/1/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/6/2024 | Approved | TEMISTOCLES CAAL |
| Final | 12/6/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 12/6/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 12/6/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 12/6/2024 | Approved | TEMISTOCLES CAAL |