5746-5746 1/2 W 85TH PL 90045

Certificate Information: 5746-5746 1/2 W 85TH PL 90045

Application / Permit
23010-10000-03986
Plan Check / Job No.
B23LA18553
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New detached 2 story 2-unit ADU
Permit Issued
Issued on 5/18/2024
Issuing Office
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 PRANITA SHAH
Corrections Issued 10/17/2023 PRANITA SHAH
Quality Review Completed 10/18/2023 GARO TELMI
Applicant returned to address corrections 4/11/2024 PRANITA SHAH
Applicant returned to address corrections 4/19/2024 PRANITA SHAH
Plan Check Approved 5/17/2024 PRANITA SHAH
Issued 5/18/2024 APPLICANT
CofO in Progress 12/9/2024 TEMISTOCLES CAAL
Permit Finaled 12/10/2024 RICHARD STEINBACH
CofO Issued 12/10/2024 RICHARD STEINBACH
Permit Finaled 12/10/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/25/2023 DINAH GARIN
Highway dedication Cleared 10/25/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/27/2023 DINAH GARIN
Sewer availability Cleared 10/27/2023 DINAH GARIN
Grading Pre-Inspection Cleared 11/20/2023 ALEXANDER HELFER
Construction near power lines Cleared 12/27/2023 RIDWAN HARDY
Specific Plan Cleared 1/30/2024 JOSHUA JONES
Low Impact Development (LID) Cleared 2/14/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 2/28/2024 DINAH GARIN
GPI Written Notices Cleared 5/17/2024 PRANITA SHAH

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/22/2024 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/30/2024 Corrections Issued BOBBY KEY
Deputy Drilled-In Anchors 6/21/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 6/21/2024 Approved BOBBY KEY
Deputy Wood Construction 7/12/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Approved BOBBY KEY
PLUMBING-Rough 8/2/2024 Approved BOBBY KEY
Sewer 8/2/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/7/2024 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 8/7/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 8/14/2024 Approved BOBBY KEY
Green Building Rough 8/14/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/14/2024 Partial Approval BOBBY KEY
Insulation 8/19/2024 Approved DANIEL VERA
Drywall Nailing 8/28/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/28/2024 Approved BOBBY KEY
Green Building Final 10/31/2024 Not Ready for Inspection TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready TEMISTOCLES CAAL
Service/Power Release 10/31/2024 Not Ready for Inspection TEMISTOCLES CAAL
Smoke Detectors 10/31/2024 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 11/1/2024 Corrections Issued TEMISTOCLES CAAL
Final 11/1/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 11/1/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 11/1/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Required TEMISTOCLES CAAL
Smoke Detectors 11/1/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 12/6/2024 Approved TEMISTOCLES CAAL
Final 12/6/2024 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 12/6/2024 Approved TEMISTOCLES CAAL
HVAC-Final 12/6/2024 Approved TEMISTOCLES CAAL
Service/Power Release 12/6/2024 Approved TEMISTOCLES CAAL