4138 N SUNNYSLOPE AVE 91423
Certificate Information: 4138 N SUNNYSLOPE AVE 91423
- Application / Permit
- 23010-10000-03949
- Plan Check / Job No.
- B23LA18380
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New detached ADU with attached trellis per GCS 65852.2 (e)(1)(B) and LAMC 12.22 A.33(c), (d) and (g). Design per licensed engineer.
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- CofO Issued on 2/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2023 | CAROLEAN BASMA |
| Corrections Issued | 10/5/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 6/17/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 6/20/2024 | AMY GUEVARRA |
| Plan Check Approved | 6/28/2024 | AMY GUEVARRA |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 2/3/2026 | JOSE AVILA |
| Permit Finaled | 2/9/2026 | RUBEN SALAS |
| CofO Issued | 2/9/2026 | RUBEN SALAS |
| Permit Finaled | 2/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/5/2023 | CAROLEAN BASMA |
| Construction near power lines | Cleared | 1/9/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/6/2024 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| DANIEL ORRANTE, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/8/2024 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/16/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 7/19/2024 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/12/2024 | Partial Inspection | JUAN VALENZUELA |
| Shower Pan | 8/20/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 8/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 8/23/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 8/27/2024 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 8/27/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 8/29/2024 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/30/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 8/30/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/5/2024 | Not Ready for Inspection | JOSE AVILA |
| Verify Sprinkler Sign Off | 9/5/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/9/2024 | Not Ready for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 9/12/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/22/2024 | Approved | JOSE AVILA |
| HVAC-Final | 1/29/2025 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 1/29/2025 | Partial Inspection | JUAN VALENZUELA |
| Drywall Nailing | 2/12/2025 | Approved | JOSE AVILA |
| HVAC-Final | 2/12/2025 | Approved | JOSE AVILA |
| Insulation | 2/12/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/18/2025 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 2/26/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/27/2025 | Approved | JOSE AVILA |
| HVAC-Final | 2/27/2025 | Approved | JOSE AVILA |
| Final | 7/25/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Required | JOSE AVILA |
| Service/Power Release | 7/25/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 7/25/2025 | Approved | JOSE AVILA |
| Final | 1/27/2026 | Corrections Issued | JOSE AVILA |
| Final | 2/3/2026 | OK to Issue CofO | JOSE AVILA |