13602 W MORRISON ST 91423

Certificate Information: 13602 W MORRISON ST 91423

Application / Permit
23010-10000-03924
Plan Check / Job No.
B23LA18276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 2 story S.F.D with Attached 2 car garage. To be fully sprinklered.
Permit Issued
Issued on 2/12/2024
Issuing Office
Current Status
CofO Issued on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 MARCELA FRANQUEZ
Corrections Issued 10/7/2023 MARCELA FRANQUEZ
Quality Review Completed 10/20/2023 TU HUA
Plan Check Approved 2/8/2024 MARCELA FRANQUEZ
Issued 2/12/2024 APPLICANT
CofO in Progress 12/7/2024 MISAEL ESPARZA
Permit Finaled 1/7/2025 RUBEN SALAS
CofO Issued 1/7/2025 RUBEN SALAS
Permit Finaled 1/7/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2023 CARLOS AGUILERA
Sewer availability Cleared 10/18/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/20/2023 LAVEON RIDER
Address approval Cleared 11/1/2023 BRYAN GODINEZ
Low Impact Development (LID) Cleared 11/20/2023 MELINEH AGHAKHABIAN
Permit Cleared 11/20/2023 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 11/20/2023 BRYAN GODINEZ
ZI Cleared 11/20/2023 ALEX VELA
Trees in Parkway Cleared 1/3/2024 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/5/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/14/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/18/2024 Partial Approval JUAN VALENZUELA
Underground Mechanical 3/18/2024 Approved JUAN VALENZUELA
Deputy Reinf. Concrete 3/19/2024 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/19/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/21/2024 Approved MISAEL ESPARZA
Deputy Wood Construction 4/8/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 4/12/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 4/25/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval MISAEL ESPARZA
Deputy Steel/Welding 4/30/2024 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 5/6/2024 Approved MISAEL ESPARZA
HVAC-Rough 5/20/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/23/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 5/23/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/24/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/24/2024 Not Ready for Inspection MISAEL ESPARZA
Structural Steel Frame 5/24/2024 Partial Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 5/24/2024 Approved MISAEL ESPARZA
Wood Frame 5/24/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/29/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 5/29/2024 Approved MISAEL ESPARZA
Green Building Rough 5/29/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 5/29/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/4/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 6/5/2024 Partial Approval MISAEL ESPARZA
Shower Pan 6/5/2024 Approved MISAEL ESPARZA
Insulation 6/14/2024 Approved MISAEL ESPARZA
Drywall Nailing 6/27/2024 Approved JOHN COLEMAN
Green Building Rough 6/27/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/27/2024 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 7/25/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Final 11/27/2024 Corrections Issued MISAEL ESPARZA
Final 11/27/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/27/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 11/27/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 11/27/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 11/27/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/27/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 12/4/2024 Approved MISAEL ESPARZA
Final 12/4/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 12/4/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 12/4/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 12/4/2024 Approved MISAEL ESPARZA
Service/Power Release 12/4/2024 Not Ready for Inspection MISAEL ESPARZA
Final 12/6/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 12/6/2024 Approved MISAEL ESPARZA
HVAC-Final 12/6/2024 Approved MISAEL ESPARZA
Service/Power Release 12/6/2024 Approved MISAEL ESPARZA