121 N MATHEWS ST 1-40 90033

Certificate Information: 121 N MATHEWS ST 1-40 90033

Application / Permit
23010-10000-03864
Plan Check / Job No.
B23LA17936
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
*eplan* NEW 4 STORY TYPE VA 40 UNITS (INCLUDING 31 LOW, 8 MODERATE INCOME, AND 1 MANAGER UNIT) AFFORDABLE HOUSING APARTMENT, 12.22.A.25 WITH INCENTIVES. TYPE VA.
Permit Issued
Issued on 4/1/2025
Issuing Office
Current Status
Issued on 4/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 CAROLYNN NEPOMUCENO
Assigned to Zoning Architect 9/28/2023 ERIC ROMERO
Corrections Issued 10/3/2023 CAROLYNN NEPOMUCENO
Quality Review Completed 10/4/2023 EUGENE BARBEAU
Plan Check Approved 2/10/2025 VU NGUYEN
Issued 4/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/8/2023 JESSICA OPINION
Hydrant and Access approval Cleared 1/30/2024 LAVEON RIDER
Construction near power lines Cleared 2/23/2024 RIDWAN HARDY
Green Code Cleared 3/18/2024 CAROLYNN NEPOMUCENO
DAS Clearance Cleared 3/19/2024 CAROLYNN NEPOMUCENO
Eng Process Fee Ord 176,300 Cleared 3/21/2024 JESSICA OPINION
Sewer availability Cleared 3/21/2024 JESSICA OPINION
Disturb/Remove Protected Trees Cleared 5/1/2024 ADALBERTO VERA
Methane Ordinance Cleared 5/28/2024 WILLIAM JOHNS
Low Impact Development (LID) Cleared 6/4/2024 ORVAL HERNANDEZ-MARCI
SB8 RUD Cleared 6/4/2024 LOUIE MILLER
Roof/Waste drainage to street Cleared 6/11/2024 JESSICA OPINION
Fire Marshal Fire Life Safety Cleared 6/13/2024 RONILO MULAWIN
Building over 36-ft Cleared 6/17/2024 CALOSHA APPROVED
GPI Written Notices Cleared 6/17/2024 CAROLYNN NEPOMUCENO
Grading Pre-Inspection Cleared 6/17/2024 CAROLYNN NEPOMUCENO
Clean Up Green Up Cleared 6/18/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/18/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/18/2024 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 6/26/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/26/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/26/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/26/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/26/2024 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 6/26/2024 RUBEN VASQUEZ
Demo/Removal of Rental Units Cleared 9/23/2024 AMANDA POSTMAN
Public Housing Cleared 12/16/2024 JESUS VALDEZ JR
Density Bonus Cleared 12/17/2024 LOUIE MILLER
Zoning Plan Check Cleared 2/6/2025 Rodolfo Arias

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: C35492 20140 ZIMMERMAN PLACE      SANTA CLARITA, CA 91390
Contractor Category Construction Llc; Lic. No.: 1041679-B 8300 MELROSE AVE PH3      WEST HOLLYWOOD, CA 90069
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

No Data Available.

Pending Inspections

Wood Frame 7/24/2026   
Green Building Rough 7/24/2026   
Insulation 7/24/2026   
Verify Sprinkler Sign Off 7/24/2026   
METHANE-Rough 7/24/2026   

Inspection Request History

Pre-Inspection 4/18/2025 Partial Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 7/9/2025 Not Ready for Inspection RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 8/27/2025 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 10/7/2025 Partial Approval RAFAEL CORTES
METHANE-Barrier 10/7/2025 Partial Approval RAFAEL CORTES
METHANE-Subgrade 10/7/2025 Partial Approval RAFAEL CORTES
Deputy Reinf. Concrete 10/30/2025 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/30/2025 Not Ready for Inspection RAFAEL CORTES
METHANE-Subgrade 10/30/2025 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 10/31/2025 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 11/26/2025 Approved RAFAEL ESPINOZA
Deputy Methane Barrier 12/4/2025 Conditional Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 12/4/2025 Partial Approval RONALD JIMENEZ
Green Building Rough 12/16/2025 Not Ready for Inspection RONALD JIMENEZ
METHANE-Rough 12/16/2025 Not Ready for Inspection RONALD JIMENEZ
Pre-Inspection 12/16/2025 Approved RONALD JIMENEZ
Verify Sprinkler Sign Off 12/16/2025 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Partial Approval RAFAEL CORTES
Pre-Inspection 2/9/2026 Approved RAFAEL CORTES
Green Building Rough 2/23/2026 Not Ready for Inspection RAFAEL CORTES
METHANE-Rough 2/23/2026 Partial Approval RAFAEL CORTES
Pre-Inspection 2/23/2026 Approved RAFAEL CORTES
Verify Sprinkler Sign Off 2/23/2026 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/9/2026 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/13/2026 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Partial Approval PAUL BAZERKANIAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2026 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 4/15/2026 Not Ready for Inspection RAFAEL CORTES
METHANE-Subgrade 4/15/2026 Approved RAFAEL CORTES
Pre-Inspection 4/17/2026 Approved RAFAEL CORTES
Footing/Foundation/Slab 4/21/2026 Partial Approval RONALD JIMENEZ
Wood Frame 4/21/2026 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 5/6/2026 Partial Approval RAFAEL CORTES
Deputy Wood Construction 5/21/2026 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 5/21/2026 Partial Approval RONALD JIMENEZ
Green Building Rough 5/21/2026 Not Ready for Inspection RONALD JIMENEZ
METHANE-Rough 5/21/2026 Not Ready for Inspection RONALD JIMENEZ
Verify Sprinkler Sign Off 5/21/2026 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 5/26/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 6/1/2026 Partial Approval RONALD JIMENEZ
Drywall Nailing 6/4/2026 Partial Approval RAFAEL CORTES
Insulation 6/11/2026 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 6/17/2026 Partial Approval RONALD JIMENEZ
Insulation 6/17/2026 Partial Approval RONALD JIMENEZ
Drywall Nailing 6/23/2026 Partial Approval RONALD JIMENEZ
Drywall Nailing 6/25/2026 Partial Approval RAFAEL CORTES
Wood Frame 6/25/2026 Partial Approval RAFAEL CORTES
Insulation 6/29/2026 Partial Approval RAFAEL CORTES
Wood Frame 7/7/2026 Partial Approval ALFREDO LOPEZ
Insulation 7/9/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 7/13/2026 Partial Approval RAFAEL ESPINOZA
Insulation 7/13/2026 Partial Approval RAFAEL ESPINOZA
Wood Frame 7/13/2026 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/15/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 7/20/2026 Partial Approval RAFAEL CORTES
Insulation 7/21/2026 Not Ready for Inspection RAFAEL CORTES
Insulation 7/23/2026 Partial Approval RAFAEL CORTES