9416-9416 1/2 S COMPTON AVE 90002
Certificate Information: 9416-9416 1/2 S COMPTON AVE 90002
- Application / Permit
- 23010-10000-03862
- Plan Check / Job No.
- B23LA17383
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: (N) 1-STORY DUPLEX
- Permit Issued
- Issued on 1/5/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | DANIEL YIP |
| Corrections Issued | 9/24/2023 | DANIEL YIP |
| Quality Review Completed | 9/26/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/20/2023 | DANIEL YIP |
| Applicant returned to address corrections | 11/22/2023 | DANIEL YIP |
| Plan Check Approved | 1/4/2024 | DANIEL YIP |
| Issued | 1/5/2024 | APPLICANT |
| CofO in Progress | 11/27/2024 | ANTHONY EGSON |
| CofO Issued | 12/30/2024 | ANSON MAGLASANG |
| Permit Finaled | 12/30/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/14/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 11/16/2023 | LAVEON RIDER |
| Frnt yard landscape/Water mgmt | Cleared | 11/22/2023 | SPENCER WEJROWSKI |
| Low Impact Development (LID) | Cleared | 12/15/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 1/2/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2024 | Corrections Issued | JOHN KLARIN |
| Pre-Inspection | 1/10/2024 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 1/19/2024 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 2/8/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | JAMES CHAVEZ |
| Underground Mechanical | 2/14/2024 | Partial Approval | JAMES CHAVEZ |
| Special/Order Compliance | 2/16/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 2/16/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 2/16/2024 | Partial Approval | BEN MOLSTAD |
| Insulation | 2/23/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/29/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 3/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/25/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 4/25/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 4/25/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/29/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 4/29/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 4/29/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/2/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 5/2/2024 | Approved | BEN MOLSTAD |
| Underground Mechanical | 5/16/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 5/23/2024 | Approved | BEN MOLSTAD |
| Insulation | 5/23/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/23/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 5/23/2024 | Approved | BEN MOLSTAD |
| Wood Frame | 5/23/2024 | Approved | BEN MOLSTAD |
| Insulation | 5/24/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 6/10/2024 | Approved | BEN MOLSTAD |
| Deputy Reinf. Concrete | 6/25/2024 | Conditional Approval | JAMES CHAVEZ |
| Reinforced Concrete Frame | 6/26/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 7/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 7/18/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Ready | BEN MOLSTAD |
| ELECTRICAL-Final | 7/22/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 7/22/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/22/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 7/22/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 7/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 7/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 9/17/2024 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 9/17/2024 | Approved | ANSON MAGLASANG |
| Service/Power Release | 9/17/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 9/17/2024 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 9/24/2024 | Approved | BARRY HACHE |
| Final | 9/24/2024 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 9/24/2024 | Approved | BARRY HACHE |
| PLUMBING-Final | 9/24/2024 | Approved | BARRY HACHE |
| Service/Power Release | 9/24/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 11/22/2024 | Approved | ANTHONY EGSON |
| Service/Power Release | 11/22/2024 | Approved | ANTHONY EGSON |
| Final | 11/27/2024 | OK to Issue CofO | ANTHONY EGSON |