14608 W ADDISON ST 91403

Certificate Information: 14608 W ADDISON ST 91403

Application / Permit
23010-10000-03861
Plan Check / Job No.
B23LA17894
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED ADU PER STATE LAW
Permit Issued
Issued on 2/3/2024
Issuing Office
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2023 APPLICANT
Assigned to Plan Check Engineer 10/4/2023 WEIJIAN HUANG
Corrections Issued 10/4/2023 WEIJIAN HUANG
Applicant returned to address corrections 1/3/2024 WEIJIAN HUANG
Plan Check Approved 1/4/2024 KHUONG TRUONG
Issued 2/3/2024 APPLICANT
CofO in Progress 1/16/2025 JACK KARGODORIAN
Permit Finaled 2/4/2025 RUBEN SALAS
CofO Issued 2/4/2025 RUBEN SALAS
Permit Finaled 2/4/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 11/1/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/13/2023 TAL SHEMEN
ZI Cleared 11/13/2023 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 12/6/2023 TAL SHEMEN
Address approval Cleared 12/12/2023 TAL SHEMEN
Sewer availability Cleared 12/12/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Herrera,, Edgar E; Lic. No.: NA67603       ,
Engineer Markarian,, Mardiros; Lic. No.: C53434 3814 VANALDEN AVE      TARZANA, CA 91356

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/6/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/13/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 2/26/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 2/28/2024 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 2/28/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/4/2024 No Access for Inspection THOMAS FINNILA
Underground Mechanical 3/4/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/8/2024 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 3/8/2024 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/15/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 3/15/2024 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 4/10/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 4/10/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 4/26/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 4/26/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 4/26/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/26/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 4/26/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/30/2024 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 5/30/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 5/30/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Approval JACK KARGODORIAN
HVAC-Rough 5/30/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 5/30/2024 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 5/30/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/4/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 6/12/2024 Approved SALVADOR MARTINEZ
Shower Pan 6/12/2024 Approved SALVADOR MARTINEZ
Insulation 6/14/2024 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 6/14/2024 Approved JACK KARGODORIAN
Drywall Nailing 6/28/2024 Approved JACK KARGODORIAN
ELECTRICAL-Final 11/7/2024 Corrections Issued JACK KARGODORIAN
HVAC-Final 11/7/2024 Corrections Issued JACK KARGODORIAN
PLUMBING-Final 11/7/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 11/27/2024 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 11/27/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 11/27/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/30/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 1/2/2025 Approved JACK KARGODORIAN
Service/Power Release 1/2/2025 Not Ready for Inspection JACK KARGODORIAN
Final 1/14/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 1/14/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 1/14/2025 Approved JACK KARGODORIAN
Smoke Detectors 1/14/2025 Approved JACK KARGODORIAN
Final 1/16/2025 OK to Issue CofO JACK KARGODORIAN