1263 S MEADOWBROOK AVE 90019
Certificate Information: 1263 S MEADOWBROOK AVE 90019
- Application / Permit
- 23010-10000-03819
- Plan Check / Job No.
- B23LA17759
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan (N) DETACHED 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- Current Status
- Issued on 2/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/7/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/20/2023 | TU HUA |
| Applicant returned to address corrections | 1/31/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 2/2/2024 | MAHNAZ NOURHASHEMI |
| Issued | 2/7/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2023 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 11/16/2023 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 1/16/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/19/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 8/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Rough | 8/29/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 9/4/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 9/4/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 9/9/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 9/9/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/24/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/24/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 10/28/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 11/5/2024 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/5/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 11/5/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/12/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| Final | 4/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 4/30/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 4/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 4/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 4/30/2025 | Approved | ARTHUR NEGRETE |
| Final | 5/30/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Final | 5/30/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 5/30/2025 | Approved | ARTHUR NEGRETE |