1133 1/2 W 77TH ST 90044

Certificate Information: 1133 1/2 W 77TH ST 90044

Application / Permit
23010-10000-03818
Plan Check / Job No.
B23LA17749
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU AND GARAGE TWO STORY ADU CHECKED PER LAMC 12.22 A.33 (C) AND (D)
Permit Issued
Issued on 2/20/2024
Issuing Office
Metro
Current Status
Issued on 2/20/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 SUNMIN LEE
Corrections Issued 10/6/2023 SUNMIN LEE
Quality Review Completed 10/20/2023 KEN GILL
Building Plans Picked Up 10/27/2023 APPLICANT
Plan Check Approved 2/20/2024 SUNMIN LEE
Issued 2/20/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/18/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/22/2024 WALLIE JONG
Sewer availability Cleared 1/22/2024 WALLIE JONG
Low Impact Development (LID) Cleared 2/6/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/6/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Adefeso,, Wole; Lic. No.: C63361 1620 CENTINELA AVE 304B      INGLEWOOD, CA 90302

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/24/2024 Corrections Issued MICHAEL LEWIS
Underground Mechanical 4/24/2024 Approved MICHAEL LEWIS
Sewer 6/13/2024 Approved MICHAEL LEWIS
Underground Mechanical 6/13/2024 Partial Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/8/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/23/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 8/23/2024 Corrections Issued JOSE MACIAS
Deputy Wood Construction 10/29/2024 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 1/24/2025 Corrections Issued JOHN QUINTANILLA
Interior/Exterior Lathing 1/24/2025 Partial Approval JOHN QUINTANILLA
PLUMBING-Rough 1/24/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 1/28/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 1/28/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 2/3/2025 Corrections Issued MICHAEL LEWIS
Green Building Rough 2/3/2025 Approved MICHAEL LEWIS
HVAC-Rough 2/3/2025 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 2/3/2025 Approved MICHAEL LEWIS
HVAC-Rough 2/5/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 2/6/2025 Approved JOHN QUINTANILLA
HVAC-Rough 2/6/2025 Approved JOHN QUINTANILLA
Insulation 2/27/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 7/3/2025 Corrections Issued JOHN QUINTANILLA
Drywall Nailing 2/23/2026 Not Ready for Inspection JOHN QUINTANILLA
Insulation 2/23/2026 Approved JOHN QUINTANILLA
Drywall Nailing 2/26/2026 Approved JOHN QUINTANILLA