1206-1206 1/2 W 37TH DR 90007

Certificate Information: 1206-1206 1/2 W 37TH DR 90007

Application / Permit
23010-10000-03802
Plan Check / Job No.
B23LA16879
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] NEW DETACHED 2-STORY, TWO UNIT ADUs PER GC 66323(a)(4) -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 12/11/2025
Issuing Office
Current Status
Issued on 12/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 MAHNAZ NOURHASHEMI
Corrections Issued 9/20/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 10/6/2023 TU HUA
Applicant returned to address corrections 9/13/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 9/23/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 12/9/2025 MAHNAZ NOURHASHEMI
Issued 12/11/2025 APPLICANT

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/29/2023 JASON CHAN
ZA Case Cleared 9/29/2023 JASON CHAN
Hydrant and Access approval Cleared 11/30/2023 LAVEON RIDER
Address approval Cleared 12/8/2023 DAVID VO
Community Plan Implem. Overlay Cleared 12/8/2023 DAVID VO
Community Plan Implem. Overlay Cleared 12/19/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 1/10/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 1/18/2024 DAVID VO
Eng Process Fee Ord 176,300 Cleared 3/21/2024 DAVID LOPEZ
Sewer availability Cleared 3/21/2024 DAVID LOPEZ
DAS Clearance Cleared 5/30/2024 SHINE LIN
Community Plan Implem. Overlay Cleared 4/22/2025 MOHAMMAD HASAN
Community Plan Implem. Overlay Cleared 6/30/2025 RIDWAN HARDY

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2026 Approved SABAS ALONSO
Sewer 4/23/2026 Approved SABAS ALONSO
Underground Mechanical 4/23/2026 Approved SABAS ALONSO
Deputy Wood Construction 4/27/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/27/2026 Approved SABAS ALONSO
ELECTRICAL-Rough 5/6/2026 Approved SABAS ALONSO
Interior/Exterior Lathing 5/6/2026 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 5/28/2026 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 5/28/2026 Approved SABAS ALONSO
Green Building Rough 5/28/2026 Approved SABAS ALONSO
HVAC-Rough 5/28/2026 Approved SABAS ALONSO
PLUMBING-Rough 5/28/2026 Approved SABAS ALONSO
Verify Sprinkler Sign Off 5/28/2026 Corrections Issued SABAS ALONSO
Insulation 6/17/2026 Approved SABAS ALONSO
Drywall Nailing 6/24/2026 Approved BRIAN SULLIVAN