4214 N BELLAIRE AVE 91604

Certificate Information: 4214 N BELLAIRE AVE 91604

Application / Permit
23010-10000-03799
Plan Check / Job No.
B23LA17676
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan" New 2 Story SFD With Attached Garage
Permit Issued
Issued on 5/14/2024
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 SUNMIN LEE
Corrections Issued 9/26/2023 SUNMIN LEE
Quality Review Completed 9/26/2023 GARO TELMI
Applicant returned to address corrections 1/16/2024 SUNMIN LEE
Applicant returned to address corrections 2/8/2024 SUNMIN LEE
Applicant returned to address corrections 2/22/2024 SUNMIN LEE
Plan Check Approved 3/8/2024 SUNMIN LEE
Issued 5/14/2024 APPLICANT
CofO in Progress 2/27/2025 JACK KARGODORIAN
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/30/2023 NIKKI ZULUETA
Permit Cleared 9/30/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/2/2023 NIKKI ZULUETA
Sewer availability Cleared 10/4/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 10/16/2023 KURT CORRAL
ZI Cleared 11/2/2023 NATHAN ROMINE
Low Impact Development (LID) Cleared 1/2/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 1/2/2024 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Plouff,, Kacie; Lic. No.: L9013 25570 RYE CANYON RD A      VALENCIA, CA 91355

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/31/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/10/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 6/10/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/11/2024 Conditional Approval DAVID MATSON
Drywall Nailing 6/14/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Conditional Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/14/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 7/12/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 7/16/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/18/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/18/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/22/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/30/2024 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 7/30/2024 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 7/30/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 7/30/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 8/7/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/9/2024 Approved MICHEL ABAJAN
Insulation 8/12/2024 Approved MICHAEL CORTEZ
Drywall Nailing 8/19/2024 Approved CHRISTOPHE COCHRAN
HVAC-Final 12/23/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Pre-Inspection 12/23/2024 Approved CHRISTOPHE COCHRAN
HVAC-Final 2/7/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 2/7/2025 Approved CHRISTOPHE COCHRAN
Final 2/10/2025 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 2/10/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 2/10/2025 Approved JACK KARGODORIAN
HVAC-Final 2/21/2025 Approved CHRISTOPHE COCHRAN
Service/Power Release 2/21/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 2/26/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 2/26/2025 Approved JACK KARGODORIAN