8941 N KESTER AVE 91402

Certificate Information: 8941 N KESTER AVE 91402

Application / Permit
23010-10000-03791
Plan Check / Job No.
B23VN11413
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d). 13D FIRE SPRINKLER THROUGH OUT.
Permit Issued
Issued on 2/25/2026
Issuing Office
Current Status
Issued on 2/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 DANIEL YIP
Corrections Issued 9/20/2023 DANIEL YIP
Quality Review Completed 9/20/2023 GARO TELMI
Applicant returned to address corrections 8/2/2024 DANIEL YIP
Applicant returned to address corrections 9/11/2024 DANIEL YIP
Plan Check Approved 10/31/2024 DANIEL YIP
Issued 2/25/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/27/2023 NIKKI ZULUETA
Address approval Cleared 10/19/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 11/14/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/14/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 8/30/2024 LAVEON RIDER
Private sewage disp. approval Cleared 10/30/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 3/6/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/12/2026 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/12/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/25/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 3/27/2026 Approved OGANES TARAKHCHYAN
Wood Frame 3/27/2026 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/29/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 5/29/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/29/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/5/2026 Approved OGANES TARAKHCHYAN
Green Building Rough 6/5/2026 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 6/5/2026 Approved OGANES TARAKHCHYAN
Insulation 6/24/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/24/2026 Partial Approval OGANES TARAKHCHYAN
Shower Pan 6/24/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 6/30/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/13/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/13/2026 Approved JAVIER RAMOS JR