1641 W 38TH ST 90062
Certificate Information: 1641 W 38TH ST 90062
- Application / Permit
- 23010-10000-03759
- Plan Check / Job No.
- B23LA17534
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED IRREGULAR SHAPED 46'-7" X 32'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/25/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/26/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/22/2024 | ALEC MOUSAKHANIAN |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 7/21/2025 | SABAS ALONSO |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
| CofO Issued | 7/21/2025 | DEROLD HAUFF |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/3/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/3/2023 | JUSTIN BICOL |
| Community Plan Implem. Overlay | Cleared | 10/26/2023 | MANERI ROMAN |
| Low Impact Development (LID) | Cleared | 1/10/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/12/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 3/26/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/4/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 9/4/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/18/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/9/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 12/5/2024 | Approved | SABAS ALONSO |
| Sewer | 12/5/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 12/5/2024 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 12/23/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/23/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | SABAS ALONSO |
| Wood Frame | 12/23/2024 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 1/7/2025 | No Access for Inspection | SABAS ALONSO |
| Shower Pan | 1/17/2025 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 1/23/2025 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 1/28/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 2/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 2/6/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/6/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | SABAS ALONSO |
| Insulation | 2/14/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 2/24/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/24/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 4/2/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/2/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 4/2/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/15/2025 | Approved | LUIS CASTRO |
| Final | 5/15/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 5/15/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 7/9/2025 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 7/9/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/17/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 7/17/2025 | Approved | SABAS ALONSO |