2809 N DUNLEER PL 90064
Certificate Information: 2809 N DUNLEER PL 90064
- Application / Permit
- 23010-10000-03729
- Plan Check / Job No.
- B23LA17371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SINGLE FAMILY DWELLING. PARKING NOT REQUIRED PER AB2097. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | ADRIANA LOPEZ |
| Corrections Issued | 10/11/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 10/13/2023 | KEN GILL |
| Building Plans Picked Up | 10/26/2023 | APPLICANT |
| Plan Check Approved | 2/22/2024 | ADRIANA LOPEZ |
| No Progress | 4/17/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 4/17/2024 | ADRIANA LOPEZ |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 5/9/2025 | RICHARD STEINBACH |
| CofO Issued | 5/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2023 | DARIN LAM |
| Permit | Cleared | 10/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/16/2023 | DARIN LAM |
| Hydrant and Access approval | Cleared | 11/3/2023 | LAVEON RIDER |
| Specific Plan | Cleared | 11/14/2023 | FREDDY GARCIA |
| Miscellaneous | Cleared | 2/15/2024 | HISASHI KOBAYAKAWA |
| Low Impact Development (LID) | Cleared | 2/21/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/21/2024 | BRENDEN HAWK |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 7/9/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 7/9/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 7/16/2024 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/16/2024 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 7/17/2024 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/31/2024 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 7/31/2024 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/9/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 9/3/2024 | Partial Inspection | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 9/25/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/25/2024 | Approved | ASHLEY THOMPSON |
| Shower Pan | 10/18/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 10/22/2024 | Approved | REGINA MENDEZ |
| HVAC-Rough | 10/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/1/2024 | Approved | DANIEL VERA |
| HVAC-Rough | 11/13/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/14/2024 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 11/14/2024 | Approved | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 11/14/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 11/22/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/22/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/22/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 12/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 12/10/2024 | Corrections Issued | REGINA MENDEZ |
| Insulation | 12/16/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/24/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 1/17/2025 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 1/17/2025 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 1/28/2025 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 2/4/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/1/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 4/1/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 4/2/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| Green Building Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| Final | 4/17/2025 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Not Required | TEMISTOCLES CAAL |
| Smoke Detectors | 4/17/2025 | Approved | TEMISTOCLES CAAL |
| Final | 5/5/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| Service/Power Release | 5/5/2025 | Approved | TEMISTOCLES CAAL |