1942 E 113TH ST 90059
Certificate Information: 1942 E 113TH ST 90059
- Application / Permit
- 23010-10000-03693
- Plan Check / Job No.
- B23LA17201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED: 2 STORY RESISDENCE WITH ATTACHED 1 CAR GARAGE AND 1 CAR CARPORT. TO BE FULLY SPRINKLERED NFPA 13D
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 10/6/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 10/11/2023 | KEN GILL |
| Building Plans Picked Up | 10/13/2023 | APPLICANT |
| Applicant returned to address corrections | 5/2/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/29/2024 | MARCELA FRANQUEZ |
| No Progress | 5/29/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/31/2024 | MARCELA FRANQUEZ |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 6/23/2025 | ANTHONY EGSON |
| CofO Issued | 6/23/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/23/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 11/2/2023 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 11/22/2023 | KURT CORRAL |
| Address approval | Cleared | 2/20/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 4/19/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 6/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 6/11/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 6/14/2024 | Partial Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 9/27/2024 | Not Ready for Inspection | BARRY HACHE |
| Deputy Wood Construction | 9/30/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/14/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/14/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 11/14/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Inspection | 11/14/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 11/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 11/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 11/20/2024 | Partial Approval | ANSON MAGLASANG |
| Special/Order Compliance | 11/20/2024 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/13/2024 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 12/13/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 12/13/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/13/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Not Ready | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/13/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 1/13/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/22/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/22/2025 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 6/6/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 6/6/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 6/6/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 6/6/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 6/6/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/11/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 6/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 6/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 6/16/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 6/16/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 6/16/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | ANTHONY EGSON |
| Final | 6/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 6/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 6/17/2025 | Approved | ANTHONY EGSON |
| Final | 6/23/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 6/23/2025 | Approved | ANTHONY EGSON |