628 E 79TH ST 1-38 90001

Certificate Information: 628 E 79TH ST 1-38 90001

Application / Permit
23010-10000-03677
Plan Check / Job No.
B23LA17170
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY WITH ROOF DECK TYPE VA 38 UNITS (29 LOW INCOME, 8 MODERATE INCOME, AND 1 MANAGER UNIT) APARTMENT, USING DENSITY BONUS INCENTIVES PER AB1763.
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
Issued on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 KEVIN MORALES
Assigned to Zoning Architect 10/5/2023 ERIC ROMERO
Corrections Issued 10/26/2023 KEVIN MORALES
Quality Review Completed 10/31/2023 EUGENE BARBEAU
Plan Check Approved 12/20/2024 VU NGUYEN
Issued 1/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/1/2023 WALLIE JONG
Highway dedication Cleared 11/1/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/2/2023 WALLIE JONG
Building over 36-ft Cleared 1/12/2024 CALOSHA APPROVED
Low Impact Development (LID) Cleared 1/22/2024 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/23/2024 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 1/30/2024 RYAN LY
Opn space landscape/Water mgmt Cleared 1/30/2024 RYAN LY
Sewer availability Cleared 2/28/2024 WALLIE JONG
"Q" conditions Cleared 5/7/2024 STEVEN WECHSLER
DAS Clearance Cleared 7/25/2024 KEVIN MORALES
Green Code Cleared 8/14/2024 KEVIN MORALES
Hydrant and Access approval Cleared 10/9/2024 LAVEON RIDER
Fire Marshal Fire Life Safety Cleared 10/23/2024 MENOA AGHAJANI
Density Bonus Cleared 12/3/2024 LOUIE MILLER
Zoning Plan Check Cleared 12/12/2024 Rodolfo Arias

Contact Information

Contractor Fico Construction; Lic. No.: 757096-B       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2025 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/11/2025 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Partial Approval RAFAEL CORTES
Green Building Rough 12/9/2025 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 12/9/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 12/9/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 1/7/2026 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 1/7/2026 Approved JOEY BUCHANAN
Wood Frame 1/7/2026 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 1/12/2026 Corrections Issued RAFAEL CORTES
Interior/Exterior Lathing 2/6/2026 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/11/2026 Partial Approval JOEY BUCHANAN
Wood Frame 3/10/2026 Partial Approval RAFAEL CORTES
Wood Frame 3/16/2026 Partial Approval RAFAEL CORTES
Insulation 3/19/2026 Partial Approval RAFAEL ESPINOZA
Insulation 3/31/2026 Partial Approval JOEY BUCHANAN
Wood Frame 5/13/2026 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 5/18/2026 Conditional Approval JOEY BUCHANAN