154 E 99TH ST 90003
Certificate Information: 154 E 99TH ST 90003
- Application / Permit
- 23010-10000-03664
- Plan Check / Job No.
- B23LA17107
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ***eplan*** NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Corrected on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | TSE MING HUANG |
| Corrections Issued | 9/18/2023 | TSE MING HUANG |
| Quality Review Completed | 9/19/2023 | EUGENE BARBEAU |
| Plan Check Approved | 12/15/2023 | TSE MING HUANG |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 7/25/2024 | BEN MOLSTAD |
| CofO Issued-Status Void | 7/25/2024 | ANSON MAGLASANG |
| Permit Finaled-Status Void | 7/25/2024 | ANSON MAGLASANG |
| Re-Activate Permit | 7/31/2024 | ANSON MAGLASANG |
| CofO Corrected | 7/31/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/31/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2023 | JEANIE LAM |
| Permit | Cleared | 9/26/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2023 | JEANIE LAM |
| Sewer availability | Cleared | 9/27/2023 | JEANIE LAM |
| Low Impact Development (LID) | Cleared | 10/12/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/16/2023 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 10/22/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Partial Approval | JAMES CHAVEZ |
| Underground Mechanical | 3/6/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | BEN MOLSTAD |
| Insulation | 3/7/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Partial Approval | JAMES CHAVEZ |
| Special/Order Compliance | 4/18/2024 | Corrections Issued | JAMES CHAVEZ |
| Special/Order Compliance | 4/19/2024 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 4/29/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 4/29/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/30/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/30/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/1/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 5/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/3/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 5/3/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/6/2024 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 5/6/2024 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 5/8/2024 | Corrections Issued | BEN MOLSTAD |
| Special/Order Compliance | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 5/10/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 5/14/2024 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 5/14/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 5/14/2024 | Approved | JAMES CHAVEZ |
| Insulation | 5/15/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | BEN MOLSTAD |
| Drywall Nailing | 5/28/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 6/26/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 7/1/2024 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 7/19/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 7/19/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/19/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/19/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 7/19/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 7/19/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 7/24/2024 | Approved | BEN MOLSTAD |
| Final | 7/24/2024 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 7/24/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/24/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 7/24/2024 | Approved | BEN MOLSTAD |