15213 W MORRISON ST 91403
Certificate Information: 15213 W MORRISON ST 91403
- Application / Permit
- 23010-10000-03659
- Plan Check / Job No.
- B23LA16028
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New detached 1-story ADU with rooftop deck per CA Govt Code 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)-(d), (g).
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | HELEN NGUYEN |
| Corrections Issued | 9/12/2023 | HELEN NGUYEN |
| Quality Review Completed | 9/12/2023 | PETER KIM |
| Applicant returned to address corrections | 11/30/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/11/2024 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/18/2024 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/24/2024 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/14/2024 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/12/2024 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/24/2024 | HELEN NGUYEN |
| Plan Check Approved | 4/29/2024 | HELEN NGUYEN |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 9/19/2025 | JACK KARGODORIAN |
| Permit Finaled | 10/15/2025 | RUBEN SALAS |
| CofO Issued | 10/15/2025 | RUBEN SALAS |
| Permit Finaled | 10/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/19/2023 | TAL SHEMEN |
| ZI | Cleared | 2/5/2024 | RYAN LY |
| Low Impact Development (LID) | Cleared | 3/22/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/29/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/7/2024 | Approved | THOMAS FINNILA |
| Underground Mechanical | 5/14/2024 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 5/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 5/30/2024 | Approved | JACK KARGODORIAN |
| Sewer | 6/5/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 7/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 8/15/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/20/2024 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/24/2024 | Partial Approval | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 9/24/2024 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Rough | 10/29/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | JACK KARGODORIAN |
| Insulation | 11/6/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 11/18/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 12/9/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/17/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 12/24/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/24/2024 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/3/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | JACK KARGODORIAN |
| Final | 9/10/2025 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Final | 9/10/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Not Required | JACK KARGODORIAN |
| Service/Power Release | 9/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 9/10/2025 | Approved | JACK KARGODORIAN |
| Final | 9/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/15/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/15/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 9/18/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 9/18/2025 | Approved | JACK KARGODORIAN |