1219 E 22ND ST 90011

Certificate Information: 1219 E 22ND ST 90011

Application / Permit
23010-10000-03656
Plan Check / Job No.
B23LA17036
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 2/13/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 DANIEL YIP
Corrections Issued 9/19/2023 DANIEL YIP
Quality Review Completed 9/20/2023 KEN GILL
Building Plans Picked Up 9/25/2023 APPLICANT
Applicant returned to address corrections 11/16/2023 DANIEL YIP
Plan Check Approved 2/8/2024 DANIEL YIP
Issued 2/13/2024 APPLICANT
CofO in Progress 11/9/2024 ALEJANDRO DE ARTOLA
Permit Finaled 11/13/2024 DEROLD HAUFF
CofO Issued 11/13/2024 DEROLD HAUFF
Permit Finaled 11/13/2024 DEROLD HAUFF

Permit Application Clearance Information

DAS Clearance Cleared 9/19/2023 SHINE LIN
Address approval Cleared 10/16/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/16/2023 STEVE MELGAR
Sewer availability Cleared 10/16/2023 STEVE MELGAR
Low Impact Development (LID) Cleared 1/31/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 2/2/2024 AMBER CAMPBELL

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/8/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/12/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 6/10/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/10/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/11/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 6/11/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/11/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/12/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/12/2024 Approved ALEJANDRO DE ARTOLA
Insulation 6/14/2024 Approved BRENDAN MORELLI
Drywall Nailing 6/25/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/25/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 6/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/16/2024 Partial Approval ALEJANDRO DE ARTOLA
Sewer 8/16/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/16/2024 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 8/16/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/22/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 8/22/2024 Approved ALEJANDRO DE ARTOLA
Gas Test 10/24/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/7/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/7/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/7/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/8/2024 Approved ALEJANDRO DE ARTOLA
Final 11/8/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 11/8/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/8/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/8/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/8/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 11/8/2024 Approved ALEJANDRO DE ARTOLA