1219 E 22ND ST 90011
Certificate Information: 1219 E 22ND ST 90011
- Application / Permit
- 23010-10000-03656
- Plan Check / Job No.
- B23LA17036
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 2/13/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | DANIEL YIP |
| Corrections Issued | 9/19/2023 | DANIEL YIP |
| Quality Review Completed | 9/20/2023 | KEN GILL |
| Building Plans Picked Up | 9/25/2023 | APPLICANT |
| Applicant returned to address corrections | 11/16/2023 | DANIEL YIP |
| Plan Check Approved | 2/8/2024 | DANIEL YIP |
| Issued | 2/13/2024 | APPLICANT |
| CofO in Progress | 11/9/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/13/2024 | DEROLD HAUFF |
| CofO Issued | 11/13/2024 | DEROLD HAUFF |
| Permit Finaled | 11/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/19/2023 | SHINE LIN |
| Address approval | Cleared | 10/16/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 10/16/2023 | STEVE MELGAR |
| Low Impact Development (LID) | Cleared | 1/31/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/2/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 6/11/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 6/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 6/14/2024 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 6/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/25/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/16/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 8/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 8/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/22/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 10/24/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/8/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |