3224 E BARBEE ST 90031

Certificate Information: 3224 E BARBEE ST 90031

Application / Permit
23010-10000-03653
Plan Check / Job No.
B23LA17009
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW ATTACHED ACCESSORY DWELLING UNIT TO (E) DETACHED GARAGE PERLAMC12.22.A33(c) and (d)
Permit Issued
Issued on 5/30/2024
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 NGHI SU
Corrections Issued 10/11/2023 RAHEL BEYENE
Quality Review Completed 10/20/2023 HERNAN ARREOLA
Plan Check Approved 5/29/2024 NGHI SU
Issued 5/30/2024 APPLICANT
CofO in Progress 5/31/2025 ALIZAH MAYAGOITIA
Permit Finaled 6/3/2025 DEROLD HAUFF
CofO Issued 6/3/2025 DEROLD HAUFF
Permit Finaled 6/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/13/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/22/2024 DAVID LOPEZ
Sewer availability Cleared 3/22/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 5/8/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/9/2024 JESSICA OPINION

Contact Information

Contractor R G E Construction; Lic. No.: 1061288-B       ,
Engineer Vega,, Cayetano Gonzalez; Lic. No.: NA43117       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 7/18/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/12/2024 Approved WILLIAM SIERRA
ELECTRICAL-Rough 12/12/2024 Approved WILLIAM SIERRA
HVAC-Rough 12/12/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 12/12/2024 Approved WILLIAM SIERRA
Sewer 12/12/2024 Approved WILLIAM SIERRA
Underground Mechanical 12/12/2024 Approved WILLIAM SIERRA
Insulation 12/31/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 1/14/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 1/14/2025 Partial Approval ANTHONY RAMOS
Insulation 1/22/2025 Approved ANTHONY RAMOS
Drywall Nailing 1/27/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 1/28/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 4/29/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/1/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/1/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/1/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 5/1/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 5/1/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/1/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 5/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 5/8/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/8/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 5/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/12/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 5/12/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/12/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 5/12/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/28/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/28/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/28/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Approved ALIZAH MAYAGOITIA
Final 5/30/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 5/30/2025 Approved ALIZAH MAYAGOITIA