10013-10013 1/2 S GRAPE ST 90002
Certificate Information: 10013-10013 1/2 S GRAPE ST 90002
- Application / Permit
- 23010-10000-03588
- Plan Check / Job No.
- B23LA16735
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DETACHED 2-STORY 2-UNIT ACCESSORY DWELLING UNIT PER STATE LAW FOR MULTI FAMILY PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | JAD BASMA |
| Corrections Issued | 10/5/2023 | JAD BASMA |
| Quality Review Completed | 10/5/2023 | GARO TELMI |
| Applicant returned to address corrections | 12/13/2023 | JAD BASMA |
| Applicant returned to address corrections | 3/12/2024 | JAD BASMA |
| Plan Check Approved | 4/25/2024 | JAD BASMA |
| Issued | 5/14/2024 | APPLICANT |
| CofO in Progress | 5/22/2026 | ARTHUR NEGRETE |
| Permit Finaled | 6/2/2026 | ANSON MAGLASANG |
| CofO Issued | 6/2/2026 | ANSON MAGLASANG |
| Permit Finaled | 6/2/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2023 | DAVID LOPEZ |
| Miscellaneous | Cleared | 10/20/2023 | JOE TAM |
| Low Impact Development (LID) | Cleared | 12/5/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/23/2024 | DAVID LOPEZ |
| "Q" conditions | Cleared | 3/18/2024 | MATHEW QUAN |
Contact Information
| Contractor | Cruz Vicente Construction Inc; Lic. No.: 914642-B | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/8/2024 | Partial Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 8/19/2024 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 8/27/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/27/2024 | Partial Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | BEN MOLSTAD |
| Gas Test | 10/17/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 10/17/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 10/17/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 10/29/2024 | Conditional Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/29/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 10/29/2024 | No Access for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/20/2024 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 11/20/2024 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 11/22/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/29/2025 | Approved | ANTHONY EGSON |
| Insulation | 5/21/2025 | Partial Approval | JOHN KLARIN |
| Drywall Nailing | 6/4/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | ANTHONY EGSON |
| Sewer | 6/4/2025 | Approved | ANTHONY EGSON |
| Underground Mechanical | 6/4/2025 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/10/2025 | Approved | JOHN KLARIN |
| Underground Mechanical | 7/2/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/16/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/16/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 9/16/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/16/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/16/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 9/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 9/16/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/10/2025 | Approved | ARTHUR NEGRETE |
| Final | 12/10/2025 | Partial Inspection | ARTHUR NEGRETE |
| HVAC-Final | 12/10/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 12/10/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 12/10/2025 | Approved | ARTHUR NEGRETE |
| Final | 4/15/2026 | Corrections Issued | ARTHUR NEGRETE |
| Final | 5/21/2026 | OK to Issue CofO | ARTHUR NEGRETE |