4833 N MURIETTA AVE 91423

Certificate Information: 4833 N MURIETTA AVE 91423

Application / Permit
23010-10000-03571
Plan Check / Job No.
B23LA16633
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) (1-STORY)
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 CARLOS MONTES
Corrections Issued 9/29/2023 CARLOS MONTES
Quality Review Completed 10/3/2023 GARO TELMI
Plan Check Approved 4/16/2024 CARLOS MONTES
Issued 4/16/2024 APPLICANT
CofO in Progress 2/4/2025 MISAEL ESPARZA
Permit Finaled 4/3/2025 RUBEN SALAS
CofO Issued 4/3/2025 RUBEN SALAS
Permit Finaled 4/3/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/23/2024 TOMMY YIN
Address approval Cleared 2/12/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/12/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/13/2024 CARLOS RAMIREZ
Sewer availability Cleared 2/13/2024 CARLOS RAMIREZ
ZI Cleared 2/13/2024 ALEX VELA
Hold Cleared 5/31/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Markarian,, Mardiros; Lic. No.: NA53434       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/18/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/18/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/19/2024 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/23/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/23/2024 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Corrections Issued MISAEL ESPARZA
Structural Steel Frame 6/4/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/25/2024 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 6/25/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 6/25/2024 Not Ready for Inspection JOHN COLEMAN
Shower Pan 6/25/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 6/25/2024 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 6/28/2024 Approved JACK KARGODORIAN
Shower Pan 6/28/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval JACK KARGODORIAN
HVAC-Rough 7/3/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/3/2024 Partial Approval JACK KARGODORIAN
Wood Frame 7/3/2024 Partial Approval JACK KARGODORIAN
Insulation 7/19/2024 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 7/19/2024 Not Ready for Inspection MISAEL ESPARZA
Insulation 7/25/2024 Approved JOSE AVILA
Drywall Nailing 8/5/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/9/2025 Corrections Issued MISAEL ESPARZA
HVAC-Final 1/9/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/9/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 1/16/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/16/2025 Approved MISAEL ESPARZA
Final 1/16/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/16/2025 Approved MISAEL ESPARZA
Green Building Final 1/16/2025 Approved MISAEL ESPARZA
Green Building Rough 1/16/2025 Approved MISAEL ESPARZA
HVAC-Final 1/16/2025 Approved MISAEL ESPARZA
MERV13>=Final 1/16/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 1/16/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 1/16/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 1/16/2025 Approved MISAEL ESPARZA
Final 1/31/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 1/31/2025 Approved MISAEL ESPARZA