4833 N MURIETTA AVE 91423
Certificate Information: 4833 N MURIETTA AVE 91423
- Application / Permit
- 23010-10000-03571
- Plan Check / Job No.
- B23LA16633
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) (1-STORY)
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | CARLOS MONTES |
| Corrections Issued | 9/29/2023 | CARLOS MONTES |
| Quality Review Completed | 10/3/2023 | GARO TELMI |
| Plan Check Approved | 4/16/2024 | CARLOS MONTES |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 2/4/2025 | MISAEL ESPARZA |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
| CofO Issued | 4/3/2025 | RUBEN SALAS |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 1/23/2024 | TOMMY YIN |
| Address approval | Cleared | 2/12/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/12/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 2/13/2024 | CARLOS RAMIREZ |
| ZI | Cleared | 2/13/2024 | ALEX VELA |
| Hold | Cleared | 5/31/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: NA53434 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/18/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/23/2024 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Structural Steel Frame | 6/4/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/25/2024 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/25/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 6/25/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Shower Pan | 6/25/2024 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 6/25/2024 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/28/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 6/28/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 7/3/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 7/19/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/19/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 7/25/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 8/5/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/16/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| Final | 1/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/16/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/16/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 1/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 1/16/2025 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 1/16/2025 | Approved | MISAEL ESPARZA |
| Final | 1/31/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 1/31/2025 | Approved | MISAEL ESPARZA |