- NEW 1-STORY 18'6" X 21' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER WFPP.
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2023 | MADISON ODELL |
| Corrections Issued | 9/12/2023 | MADISON ODELL |
| Plan Check Approved | 9/28/2023 | MADISON ODELL |
| Issued | 10/2/2023 | APPLICANT |
| CofO in Progress | 5/1/2025 | LILIANA PORTILLO |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/18/2023 | ROBERT HUGHES |
| "Q" conditions | Cleared | 9/19/2023 | YINGSHI HUANG |
| Address approval | Cleared | 9/26/2023 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 9/28/2023 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/7/2023 | Partial Approval | AMY COLIN |
| Underground Mechanical | 11/7/2023 | Corrections Issued | AMY COLIN |
| Underground Mechanical | 11/8/2023 | Partial Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 11/14/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 8/6/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/26/2024 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/10/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/10/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 10/10/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/10/2024 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/10/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/23/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Approved | LILIANA PORTILLO |
| Insulation | 10/23/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/23/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 10/23/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/31/2024 | Approved | LILIANA PORTILLO |
| Insulation | 10/31/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/31/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/31/2024 | Approved | LILIANA PORTILLO |
| Final | 3/13/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 3/13/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 3/13/2025 | Approved | LILIANA PORTILLO |
| Final | 4/9/2025 | No Access for Inspection | LILIANA PORTILLO |
| Service/Power Release | 4/9/2025 | No Access for Inspection | LILIANA PORTILLO |
| Final | 4/14/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 4/14/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/28/2025 | Approved | LILIANA PORTILLO |
| Final | 4/28/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Gas Test | 4/28/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/28/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/28/2025 | Approved | LILIANA PORTILLO |
| Service/Power Release | 4/28/2025 | Approved | LILIANA PORTILLO |