3665 N MONTEREY ROAD 90032

Certificate Information: 3665 N MONTEREY ROAD 90032

Application / Permit
23010-10000-03539
Plan Check / Job No.
B23LA16443
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 18'6" X 21' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER WFPP.
Permit Issued
Issued on 10/2/2023
Issuing Office
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/12/2023 MADISON ODELL
Corrections Issued 9/12/2023 MADISON ODELL
Plan Check Approved 9/28/2023 MADISON ODELL
Issued 10/2/2023 APPLICANT
CofO in Progress 5/1/2025 LILIANA PORTILLO
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/18/2023 ROBERT HUGHES
"Q" conditions Cleared 9/19/2023 YINGSHI HUANG
Address approval Cleared 9/26/2023 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 9/26/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 9/28/2023 AMBER CAMPBELL
Sewer availability Cleared 9/28/2023 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2023 Partial Approval AMY COLIN
Underground Mechanical 11/7/2023 Corrections Issued AMY COLIN
Underground Mechanical 11/8/2023 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 11/14/2023 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/1/2024 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 8/6/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/16/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 9/26/2024 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 10/10/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/10/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 10/10/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 10/10/2024 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 10/10/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/23/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 10/23/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved LILIANA PORTILLO
Insulation 10/23/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 10/23/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 10/23/2024 Approved LILIANA PORTILLO
Drywall Nailing 10/31/2024 Approved LILIANA PORTILLO
Insulation 10/31/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/31/2024 Approved LILIANA PORTILLO
Shower Pan 10/31/2024 Approved LILIANA PORTILLO
Final 3/13/2025 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 3/13/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 3/13/2025 Approved LILIANA PORTILLO
Final 4/9/2025 No Access for Inspection LILIANA PORTILLO
Service/Power Release 4/9/2025 No Access for Inspection LILIANA PORTILLO
Final 4/14/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 4/14/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 4/28/2025 Approved LILIANA PORTILLO
Final 4/28/2025 OK to Issue CofO LILIANA PORTILLO
Gas Test 4/28/2025 Approved LILIANA PORTILLO
HVAC-Final 4/28/2025 Approved LILIANA PORTILLO
PLUMBING-Final 4/28/2025 Approved LILIANA PORTILLO
Service/Power Release 4/28/2025 Approved LILIANA PORTILLO